CPWD Analysis of Rates · Sub-head 15

Dismantling and Demolishing

92 rate analyses from the CPWD Delhi Analysis of Rates 2023 (Civil). Each shows the full material, labour and machinery build-up. Searchable, and free to view.

Transcribed from the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, effective 2023-09-14. Reference only — verify against the official source before pricing a bid. Open any item for its full cost build-up.

92 analyses

DescriptionUnit
15.1Demolishing lime concrete manually/ by mechanical means and disposal of material within 50 metres lead as per direction of Engineerin-charge3 priced inputscum851.50
15.2.1Demolishing cement concrete manually/ by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in - chargeNominal concrete 1:3:6 or richer mix (i/c equivalent design mix)3 priced inputscum2,434.25
15.2.2Demolishing cement concrete manually/ by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in - chargeNominal concrete 1:4:8 or leaner mix (i/c equivalent design mix)3 priced inputscum1,503.60
15.3Demolishing R.C.C. work manually/ by mechanical means including stacking of steel bars and disposal of unserviceable material within 50 metres lead as per direction of Engineer - incharge3 priced inputscum3,551.25
15.4Demolishing R.B. work manually/ by mechanical means including stacking of steel bars and disposal of unserviceable material within 50 metres lead as per direction of Engineer-incharge3 priced inputscum3,177.25
15.5Extra for cutting reinforcement bars manually/ by mechanical means in R.C.C. or R.B. work (Payment shall be made on the cross sectional area of R.C.C. or R.B. work) as per direction of Engineer-in-charge3 priced inputssqm1,147.20
15.6Extra for scrapping, cleaning and straightening reinforcement from R.C.C. or R.B. work3 priced inputskg9.05
15.7.1Demolishing brick work manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-chargeIn mud mortar3 priced inputscum704.90
15.7.2Demolishing brick work manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-chargeIn lime mortar with old mughal bricks3 priced inputscum1,783.35
15.7.3Demolishing brick work manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-chargeIn lime mortar3 priced inputscum851.50
15.7.4Demolishing brick work manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-chargeIn cement mortar3 priced inputscum2,060.20
15.8.1Removing mortar from bricks and cleaning bricks including stacking within a lead of 50 m (stacks of cleaned bricks shall be measured)From brick work in mud mortar4 priced inputsNos4,658.45
15.8.2Removing mortar from bricks and cleaning bricks including stacking within a lead of 50 m (stacks of cleaned bricks shall be measured)From brick work in lime mortar4 priced inputsNos5,355.30
15.8.3Removing mortar from bricks and cleaning bricks including stacking within a lead of 50 m (stacks of cleaned bricks shall be measured)From brick work in cement mortar4 priced inputsNos6,700.80
15.9.1Demolishing stone rubble masonry manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-chargeIn lime mortar3 priced inputscum1,158.10
15.9.2Demolishing stone rubble masonry manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-chargeIn cement mortar3 priced inputscum2,458.95
15.10.1Dismantling dressed stone work ashlar face stone work, marble work or precast concrete work manually/ by mechanical means including stacking of serviceable and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-chargeIn lime mortar3 priced inputscum1,464.25
15.10.2Dismantling dressed stone work ashlar face stone work, marble work or precast concrete work manually/ by mechanical means including stacking of serviceable and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-chargeIn cement mortar3 priced inputscum2,877.75
15.11.1Removing mortar from and cleaning stones and concrete articles (net quantity of stacks of cleaned materials will be measured)In lime mortar4 priced inputscum478.55
15.11.2Removing mortar from and cleaning stones and concrete articles (net quantity of stacks of cleaned materials will be measured)In cement mortar4 priced inputscum689.20
15.12.1Dismantling doors, windows and clerestory windows (steel or wood) shutter including chowkhats, architrave, holdfasts etc. complete and stacking within 50 metres leadOf area 3 sq. metres and below4 priced inputs367.20
15.12.2Dismantling doors, windows and clerestory windows (steel or wood) shutter including chowkhats, architrave, holdfasts etc. complete and stacking within 50 metres leadOf area beyond 3 sq. metres4 priced inputs502.75
15.13.1Taking out doors, windows and clerestory window shutters (steel or wood) including stacking within 50 metres leadOf area 3 sq. metres and below3 priced inputs143.50
15.13.2Taking out doors, windows and clerestory window shutters (steel or wood) including stacking within 50 metres leadOf area beyond 3 sq. metres3 priced inputs188.90
15.14.1Dismantling wood work in frames, trusses, purlins and rafters up to 10 metres span and 5 metres height including stacking the material within 50 metres leadOf sectional area 40 square centimetres and above3 priced inputscum4,459.10
15.14.2Dismantling wood work in frames, trusses, purlins and rafters up to 10 metres span and 5 metres height including stacking the material within 50 metres leadOf sectional area below 40 square centimetres3 priced inputsmetre17.85
15.15.1Extra for dismantling trusses, rafters, purlins etc. of wood work for every additional span of one metre or part thereof beyond 10 metresOf sectional area 40 square centimetres and above3 priced inputscum per metre span589.55
15.15.2Extra for dismantling trusses, rafters, purlins etc. of wood work for every additional span of one metre or part thereof beyond 10 metresOf sectional area below 40 square centimetres3 priced inputsmetre per metre span1.65
15.16.1Extra for dismantling trusses, rafters, purlins etc. of wood work for every additional height of one metre or part thereof beyond 5 metresOf sectional area 40 square centimetres and above3 priced inputscum per metre height857.00
15.16.2Extra for dismantling trusses, rafters, purlins etc. of wood work for every additional height of one metre or part thereof beyond 5 metresOf sectional area below 40 square centimetres3 priced inputsmetre per metre height3.40
15.17.1Dismantling steel work in single sections including dismembering and stacking within 50 metres lead inR.S. Joists4 priced inputsquintal3.40
15.17.2Dismantling steel work in single sections including dismembering and stacking within 50 metres lead inChannels, angles, tees and flats4 priced inputsquintal2.30
15.18Dismantling steel work in built up sections in angles, tees, flats and channels including all gusset plates, bolts, nuts, cutting rivets, welding etc. including dismembering and stacking within 50 metres lead4 priced inputsquintal5.65
15.19Dismantling steel work manually/ by mechanical means in built up sections without dismembering and stacking within 50 metres lead as per direction of Engineer-in-charge3 priced inputsquintal3.85
15.20Extra for dismantling trusses, rafters, purlins etc. of steel work for every additional span of one metre or part thereof beyond 10 metres3 priced inputsquintal per metre span0.85
15.21Extra for dismantling trusses, rafters, purlins etc. of steel work for every additional height of one metre or part thereof beyond 5 metres3 priced inputsquintal per metre height0.85
15.22Extra for marking of structural steel work required to be re-erected2 priced inputsquintal4.65
15.23.1Dismantling tile work in floors and roofs laid in cement mortar including stacking material within 50 metres leadFor thickness of tiles 10 mm to 25 mm4 priced inputssqm73.40
15.23.2Dismantling tile work in floors and roofs laid in cement mortar including stacking material within 50 metres leadFor thickness of tiles above 25 mm and up to 40 mm4 priced inputssqm113.35
15.24Demolishing dry brick pitching in floors, drains etc. including stacking of serviceable material and disposal of unserviceable material within 50 metres lead :3 priced inputscum1,317.65
15.25Dismantling stone slab flooring laid in cement mortar including stacking of serviceable material and disposal of unserviceable material within 50 metres lead3 priced inputssqm266.45
15.26Demolishing brick tile covering in terracing including stacking of serviceable material and disposal of unserviceable material within 50 metres lead4 priced inputssqm105.35
15.27Demolishing mud phaska in terracing and disposal of material within 50 metres lead3 priced inputscum914.30
15.28.1Dismantling roofing including ridges, hips, valleys and gutters etc., and stacking the material within 50 metres lead ofG.S. Sheet3 priced inputssqm164.95
15.28.2Dismantling roofing including ridges, hips, valleys and gutters etc., and stacking the material within 50 metres lead ofAsbestos Cement sheet3 priced inputssqm77.30
15.29Dismantling stone slab roofing over wooden karries or R.C.C. battens (dismantling karries and battens to be paid for separately), including stacking of serviceable material and disposal of unserviceable material within 50 metres lead3 priced inputscum2,664.65
15.30Dismantling jack arch roofing and floors including stacking of serviceable material and disposal of unserviceable material within 50 metres lead3 priced inputssqm253.90
15.31Dismantling tiled roofing with battens, boarding etc. complete including stacking of serviceable material and disposal of unserviceable material within 50 metres lead3 priced inputssqm209.90
15.32Demolishing thatch roofing including mats, bamboo, jaffari etc. complete including stacking of serviceable material and disposal of unserviceable material within 50 metres lead2 priced inputssqm57.70
15.33Dismantling wooden ballies in posts and struts including stacking within 50metres lead3 priced inputsmetre20.95
15.34.1Dismantling and stacking within 50 metres lead, fencing posts or struts including all earth work and dismantling of concrete etc. in base ofT’ or ‘L’ iron or pipe5 priced inputs230.90
15.34.2Dismantling and stacking within 50 metres lead, fencing posts or struts including all earth work and dismantling of concrete etc. in base ofR.C.C6 priced inputs243.30
15.35Cutting ballies or wooden posts of fencing at the point of projection above the concrete or ground and stacking the same within 50 metres lead2 priced inputsballie13.45
15.36Dismantling barbed wire or flexible wire rope in fencing including making rolls and stacking within 50 metres lead2 priced inputsquintal36.80
15.37Dismantling wooden trellis work excluding frames but including stacking the serviceable material within 50 metres lead4 priced inputssqm64.85
15.38Dismantling expanded metal or I.R.C. fabrics with necessary battens and beading including stacking the serviceable material within 50 metres lead4 priced inputssqm75.80
15.39.1Dismantling wooden boardings in lining of walls and partitions, excluding supporting members but including stacking within 50 metres leadUp to 10 mm thick4 priced inputssqm61.00
15.39.2Dismantling wooden boardings in lining of walls and partitions, excluding supporting members but including stacking within 50 metres leadThickness above 10 mm up to 25 mm4 priced inputssqm77.75
15.39.3Dismantling wooden boardings in lining of walls and partitions, excluding supporting members but including stacking within 50 metres leadThickness above 25 mm up to 40 mm4 priced inputssqm90.35
15.40.1Dismantling precast concrete or stone slabs in walls, partition walls etc. including stacking within 50 metres leadThickness up to 40 mm4 priced inputssqm289.30
15.40.2Dismantling precast concrete or stone slabs in walls, partition walls etc. including stacking within 50 metres leadThickness above 40 mm up to 75 mm4 priced inputssqm433.55
15.41Dismantling cement asbestos or other hard board ceiling or partition walls including stacking of serviceable materials and disposal of unserviceable materials within 50 metres lead3 priced inputssqm56.35
15.42.1Dismantling C.I. or asbestos rain water pipe with fittings and clamps including stacking the material within 50 metres lead75 to 80 mm dia pipe3 priced inputsmetre75.70
15.42.2Dismantling C.I. or asbestos rain water pipe with fittings and clamps including stacking the material within 50 metres lead100 mm dia pipe3 priced inputsmetre78.00
15.42.3Dismantling C.I. or asbestos rain water pipe with fittings and clamps including stacking the material within 50 metres lead150 mm dia pipe3 priced inputsmetre80.25
15.43.1Dismantling manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-chargeWater bound macadam road3 priced inputssqm217.45
15.43.2Dismantling manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-chargebituminous road3 priced inputssqm428.50
15.44.1Dismantling G.I. pipes (external work) including excavation and refilling trenches after taking out the pipes, manually/ by mechanical means including stacking of pipes within 50 metres lead as per direction of Engineer-in-charge15 mm to 40 mm nominal bore3 priced inputsmetre149.80
15.44.2Dismantling G.I. pipes (external work) including excavation and refilling trenches after taking out the pipes, manually/ by mechanical means including stacking of pipes within 50 metres lead as per direction of Engineer-in-chargeAbove 40 mm nominal bore3 priced inputsmetre161.40
15.45.1Dismantling C.I. pipes including excavation and refilling trenches after taking out the pipes, manually/ by mechanical means breaking lead caulked joints, melting of lead and making into blocks including stacking of pipes & lead at site within 50 metre lead as per direction of Engineer-in-chargeUp to 150 mm diameter7 priced inputsmetre332.40
15.45.2Dismantling C.I. pipes including excavation and refilling trenches after taking out the pipes, manually/ by mechanical means breaking lead caulked joints, melting of lead and making into blocks including stacking of pipes & lead at site within 50 metre lead as per direction of Engineer-in-chargeAbove 150 mm dia up to 300 mm dia7 priced inputsmetre456.65
15.45.3Dismantling C.I. pipes including excavation and refilling trenches after taking out the pipes, manually/ by mechanical means breaking lead caulked joints, melting of lead and making into blocks including stacking of pipes & lead at site within 50 metre lead as per direction of Engineer-in-chargeAbove 300 mm diameter7 priced inputsmetre614.30
15.46.1Dismantling steel cylinder R.C. pipes including excavation and refilling trenches after taking out the pipes, manually/ by mechanical means breaking lead caulked joints, melting of lead and making into blocks including stacking of pipes & lead at site within 50 metres lead as per direction of Engineer-in-chargeUp to 600 mm diameter8 priced inputsmetre695.25
15.46.2Dismantling steel cylinder R.C. pipes including excavation and refilling trenches after taking out the pipes, manually/ by mechanical means breaking lead caulked joints, melting of lead and making into blocks including stacking of pipes & lead at site within 50 metres lead as per direction of Engineer-in-chargeAbove 600 mm diameter8 priced inputsmetre1,752.45
15.47.1Dismantling asbestos cement pressure pipes including excavation and refilling trenches after taking out the pipes manually/ by mechanical means and stacking the pipes within 50 metres lead as per direction of Engineer-in-chargeUp to 150 mm diameter6 priced inputsmetre332.15
15.47.2Dismantling asbestos cement pressure pipes including excavation and refilling trenches after taking out the pipes manually/ by mechanical means and stacking the pipes within 50 metres lead as per direction of Engineer-in-chargeAbove 150 mm diameter6 priced inputsmetre403.05
15.48Taking out C.I. cover with frame from R.C.C. top slab of manholes of various sizes including demolishing of R.C.C. work manually/ by mechanical means and stacking of useful materials near the site and disposal of unserviceable materials within 50 metres lead as per direction of Engineer-in-charge4 priced inputsman697.40
15.49Taking out C.I. cover with frame from R.C.C. top slab of inspection chambers of various sizes including demolishing of R.C.C. work manually/ by mechanical means and stacking of useful materials near the site and disposal of unserviceable materials within 50 metres lead as per direction of Engineer-in-charge4 priced inputsman406.75
15.50Dismantling of R.C.C. spun vent shaft including excavating the cement concrete pit completely, taking out the shaft, refilling the excavated gap, stacking the useful materials near the site and disposal of unserviceable materials within 50 metres lead12 priced inputs4,623.70
15.51Dismantling of road gully chamber of various sizes including C.I. grating with frame including stacking of useful materials near the site and disposal of unserviceable materials within 50 metres lead including refilling the excavated gap10 priced inputsone chamber958.75
15.52Dismantling of flushing cistern of all types (C.I./PVC/Vitrious China) including stacking of useful materials near the site and disposal of unserviceable materials within 50 metres lead3 priced inputs112.05
15.53.1Dismantling of C.I. sluice valve including stacking of useful materials within a lead of 50 metresUp to 150 mm diameter4 priced inputsdismantling 10319.50
15.53.2Dismantling of C.I. sluice valve including stacking of useful materials within a lead of 50 metresAbove 150 mm diameter4 priced inputsdismantling 101,184.15
15.54Dismantling of spindle fire hydrant including stacking of useful materials within 50 metres lead3 priced inputsNos726.35
15.55.1Dismantling of cement concrete platform along with curtain walls and base concrete etc. including stacking of useful materials near the site and disposal of unserviceable materials within 50 metres lead120 x 120 cm (outside to outside)9 priced inputsone platform1,104.05
15.55.2Dismantling of cement concrete platform along with curtain walls and base concrete etc. including stacking of useful materials near the site and disposal of unserviceable materials within 50 metres lead210 x 120 cm (outside to outside)9 priced inputsone platform1,693.35
15.55.3Dismantling of cement concrete platform along with curtain walls and base concrete etc. including stacking of useful materials near the site and disposal of unserviceable materials within 50 metres lead320 x 120 cm (outside to outside)9 priced inputsone platform2,396.95
15.56Dismantling old plaster or skirting raking out joints and cleaning the surface for plaster including disposal of rubbish to the dumping ground within 50 metres lead4 priced inputssqm54.65
15.57Dismantling aluminium/ Gypsum partitions, doors, windows, fixed glazing and false ceiling including disposal of unserviceable material and stacking of serviceable material with in 50 meters lead as directed by Engineer-in-charge3 priced inputssqm56.35
15.58Demolishing R.C.C. work by mechanical means and stockpiling at designated locations and disposal of dismantled materials up to a lead of 1 kilometre, stacking serviceable and unserviceable material separately including cutting reinforcement bars8 priced inputscum2,818.90
15.59Dismantling of flexible pavement (bituminous courses) by mechanical means and disposal of dismantled material up to a lead of 1 kilometre, as per direction of Engineer-in-charge4 priced inputscum420.80
15.60Disposal of building rubbish / malba / similar unserviceable, dismantled or waste materials by mechanical means, including loading, transporting, unloading to approved municipal dumping ground or as approved by Engineer-in-charge, beyond 50 m initial lead, for all leads including all lifts involved1 priced inputscum263.95

Pricing dismantling and demolishing for a live tender

Each analysis here is the CPWD base; a real estimate adjusts it for the project's inputs and the current cost index, then maps it back to the tender's BOQ. Arched's estimation engine does that mapping and flags where the numbers are exposed before submission.

See how estimation works