Dismantling C.I. or asbestos rain water pipe with fittings and clamps including stacking the material within 50 metres lead

150 mm dia pipe
Item number
15.42.3
Analysis basis
10 metre
Priced inputs
3
Derived rate
₹80.25/ METRE
D-01/RATE ANALYSISITEM 15.42.3

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.42.3 (Dismantling C.I. or asbestos rain water pipe with fittings and clamps including stacking the material within 50 metres lead : 150 mm dia pipe) is derived from 3 priced inputs for 10 metre and works out to ₹80.25 per metre after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 15.42.3DETAIL OF COST FOR 10 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0114LABBeldarday0.36736.00264.96
0115LABCoolieday0.4736.00294.40
9999MATSundriesL.S.2.082.274.72
BUILD-UP TO RATE
TOTAL
564.08
Add 1 % Water charges on “W”
+5.64
TOTAL
569.72
Add GST on “X” (multiplying factor 0.2127)
+121.18
TOTAL
690.90
Add 15% CPOH on “Y”
+103.64
TOTAL
794.54
Add Cess @ 1% on “Z”
+7.95
Cost of 10.00 metre
802.49
Cost of 1.00 metre
80.25
SAY
₹80.25
D-02/SOURCEPRINTED PAGE 1126
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1126

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1126. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSDISMANTLING AND DEMOLISHING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.