Dismantling manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge

Water bound macadam road
Item number
15.43.1
Analysis basis
36 sqm
Priced inputs
3
Derived rate
₹217.45/ SQM
D-01/RATE ANALYSISITEM 15.43.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.43.1 (Dismantling manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge : Water bound macadam road) is derived from 3 priced inputs for 36 sqm and works out to ₹217.45 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Consider a road 6 metres wide and 6 metres
  • length wise 25 cm average depth = 9.00 cubic
  • metre
  • For cutting road taking out soiling and metalling
  • including sorting and screening
ANALYSIS OF RATES · ITEM 15.43.1DETAIL OF COST FOR 36 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0114LABBeldarday4.8736.003,532.80
0115LABCoolieday2.4736.001,766.40
9999MATLabour for stacking of serviceable material and disposal of unserviceable material within 50 metres leadL.S.89.72.27203.62
BUILD-UP TO RATE
TOTAL
5,502.82
Add 1 % Water charges on “W”
+55.03
TOTAL
5,557.85
Add GST on “X” (multiplying factor 0.2127)
+1,182.15
TOTAL
6,740.00
Add 15% CPOH on “Y”
+1,011.00
TOTAL
7,751.00
Add Cess @ 1% on “Z”
+77.51
Cost of 36.00 sqm
7,828.51
Cost of 1.00 sqm
217.46
SAY
₹217.45
D-02/SOURCEPRINTED PAGE 1126
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1126

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1126. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSDISMANTLING AND DEMOLISHING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.