Skip to main content

Dismantling manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge

bituminous road
Item number
15.43.2
Analysis basis
36 sqm
Priced inputs
3
Derived rate
₹428.50/ SQM
D-01/RATE ANALYSISITEM 15.43.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.43.2 (Dismantling manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge : bituminous road) is derived from 3 priced inputs for 36 sqm and works out to ₹428.50 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Consider a road 6 metres wide and 6 metres
  • length wise 30 cm average depth =10.80 cubic
  • metre
  • For cutting road taking out soiling and metalling
  • including sorting and screening
ANALYSIS OF RATES · ITEM 15.43.2DETAIL OF COST FOR 36 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0114LABBeldarday9.6736.007,065.60
0115LABCoolieday4.8736.003,532.80
9999MATLabour for stacking of serviceable material and disposal of unserviceable material within 50 metres leadL.S.107.642.27244.34
BUILD-UP TO RATE
TOTAL
10,842.74
Add 1 % Water charges on “W”
+108.43
TOTAL
10,951.17
Add GST on “X” (multiplying factor 0.2127)
+2,329.31
TOTAL
13,280.48
Add 15% CPOH on “Y”
+1,992.07
TOTAL
15,272.55
Add Cess @ 1% on “Z”
+152.73
Cost of 36.00 sqm
15,425.28
Cost of 1.00 sqm
428.48
SAY
₹428.50
D-02/SOURCEPRINTED PAGE 1127
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1127

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1127. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSDISMANTLING AND DEMOLISHING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.