Dismantling manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge
- Item number
- 15.43.2
- Analysis basis
- 36 sqm
- Priced inputs
- 3
- Derived rate
- ₹428.50/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.43.2 (Dismantling manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge : bituminous road) is derived from 3 priced inputs for 36 sqm and works out to ₹428.50 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Consider a road 6 metres wide and 6 metres
- length wise 30 cm average depth =10.80 cubic
- metre
- For cutting road taking out soiling and metalling
- including sorting and screening
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0114 | LAB | Beldar | day | 9.6 | 736.00 | 7,065.60 |
| 0115 | LAB | Coolie | day | 4.8 | 736.00 | 3,532.80 |
| 9999 | MAT | Labour for stacking of serviceable material and disposal of unserviceable material within 50 metres lead | L.S. | 107.64 | 2.27 | 244.34 |
- TOTAL
- 10,842.74
- Add 1 % Water charges on “W”
- +108.43
- TOTAL
- 10,951.17
- Add GST on “X” (multiplying factor 0.2127)
- +2,329.31
- TOTAL
- 13,280.48
- Add 15% CPOH on “Y”
- +1,992.07
- TOTAL
- 15,272.55
- Add Cess @ 1% on “Z”
- +152.73
- Cost of 36.00 sqm
- 15,425.28
- Cost of 1.00 sqm
- 428.48
- SAY
- ₹428.50
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1127
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1127. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.