Dismantling G.I. pipes (external work) including excavation and refilling trenches after taking out the pipes, manually/ by mechanical means including stacking of pipes within 50 metres lead as per direction of Engineer-in-charge

15 mm to 40 mm nominal bore
Item number
15.44.1
Analysis basis
10 metre
Priced inputs
3
Derived rate
₹149.80/ METRE
D-01/RATE ANALYSISITEM 15.44.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.44.1 (Dismantling G.I. pipes (external work) including excavation and refilling trenches after taking out the pipes, manually/ by mechanical means including stacking of pipes within 50 metres lead as per direction of Engineer-in-charge : 15 mm to 40 mm nominal bore) is derived from 3 priced inputs for 10 metre and works out to ₹149.80 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Trenching and refilling etc
ANALYSIS OF RATES · ITEM 15.44.1DETAIL OF COST FOR 10 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0114LABBeldarday0.66736.00485.76
0115LABCoolieday0.66736.00485.76
9999MATDismantling G.I. pipe and stacking etcL.S.35.882.2781.45
BUILD-UP TO RATE
TOTAL
1,052.97
Add 1 % Water charges on “W”
+10.53
TOTAL
1,063.50
Add GST on “X” (multiplying factor 0.2127)
+226.21
TOTAL
1,289.71
Add 15% CPOH on “Y”
+193.46
TOTAL
1,483.17
Add Cess @ 1% on “Z”
+14.83
Cost of 10.00 metre
1,498.00
Cost of 1.00 metre
149.80
SAY
₹149.80
D-02/SOURCEPRINTED PAGE 1127
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1127

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1127. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSDISMANTLING AND DEMOLISHING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.