Dismantling G.I. pipes (external work) including excavation and refilling trenches after taking out the pipes, manually/ by mechanical means including stacking of pipes within 50 metres lead as per direction of Engineer-in-charge
- Item number
- 15.44.2
- Analysis basis
- 10 metre
- Priced inputs
- 3
- Derived rate
- ₹161.40/ METRE
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.44.2 (Dismantling G.I. pipes (external work) including excavation and refilling trenches after taking out the pipes, manually/ by mechanical means including stacking of pipes within 50 metres lead as per direction of Engineer-in-charge : Above 40 mm nominal bore) is derived from 3 priced inputs for 10 metre and works out to ₹161.40 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- Trenching and refilling etc
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0114 | LAB | Beldar | day | 0.66 | 736.00 | 485.76 |
| 0115 | LAB | Coolie | day | 0.66 | 736.00 | 485.76 |
| 9999 | MAT | Dismantling G.I. pipe and stacking etc | L.S. | 71.76 | 2.27 | 162.90 |
- TOTAL
- 1,134.42
- Add 1 % Water charges on “W”
- +11.34
- TOTAL
- 1,145.76
- Add GST on “X” (multiplying factor 0.2127)
- +243.70
- TOTAL
- 1,389.46
- Add 15% CPOH on “Y”
- +208.42
- TOTAL
- 1,597.88
- Add Cess @ 1% on “Z”
- +15.98
- Cost of 10.00 metre
- 1,613.86
- Cost of 1.00 metre
- 161.39
- SAY
- ₹161.40
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1128
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1128. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.