CPWD Analysis of Rates · Dismantling and Demolishing

Dismantling C.I. pipes including excavation and refilling trenches after taking out the pipes, manually/ by mechanical means breaking lead caulked joints, melting of lead and making into blocks including stacking of pipes & lead at site within 50 metre lead as per direction of Engineer-in-charge

Up to 150 mm diameter

Item number
15.45.1
Analysis basis
Detail of cost for 40.26 metre or 11 nos joints
Priced inputs
7
Derived rate
332.40 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.45.1 Dismantling C.I. pipes including excavation and refilling trenches after taking out the pipes, manually/ by mechanical means breaking lead caulked joints, melting of lead and making into blocks including stacking of pipes & lead at site within 50 metre lead as per direction of Engineer-in-charge: Up to 150 mm diameter — is derived from 7 priced inputs for 40.26 metre and works out to ₹332.40 per metre after water charges, GST, CPOH and cess. The full build-up is below.

  • Earth work in excavation for dismantling pipes
  • including refilling of excavated earth
  • 1x40.26x0.55x0.75 m =16.61cum
  • =1x40.26x(22/7)/4x(0.118)x(0.118) =0.44cum
  • Total =16.17cum
  • Deduct for pipes of average 100 mm dia
CodeInputUnitQuantityRate (INR)Amount (INR)
Rate as per Item No.2.8.1 of SH: EARTH WORKRate as per item 2.8.1Sub-analysiscum16.17260.304,209.05
Rate as per Item No.2.25 of SH: EARTH WORKRate as per item 2.25Sub-analysiscum16.17196.003,169.32
0761Fuel woodMaterialquintal0.46550.00253.00
0771Kerosene oilMateriallitre0.3850.0019.00
0117Assistant Fitter or 2nd class FitterLabourday0.63816.00514.08
0114BeldarLabourday4.5736.003,312.00
9977CarriageMaterialL.S.53.822.27122.17
TOTAL
11,598.62
Add 1 % Water charges on “W-A”
42.20
TOTAL
11,640.82
Add GST on “X-A” (multiplying factor 0.2127)
906.62
TOTAL
12,547.44
Add 15% CPOH on “Y-A”
775.36
TOTAL
13,322.80
Add Cess @ 1% on “Z-A”
59.44
Cost of 40.26 metre
13,382.24
Cost of 1.00 metre
332.40
Say
332.40

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1128. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.