Skip to main content

Dismantling C.I. pipes including excavation and refilling trenches after taking out the pipes, manually/ by mechanical means breaking lead caulked joints, melting of lead and making into blocks including stacking of pipes & lead at site within 50 metre lead as per direction of Engineer-in-charge

Up to 150 mm diameter
Item number
15.45.1
Analysis basis
40.26 metre
Priced inputs
7
Derived rate
₹332.40/ METRE
D-01/RATE ANALYSISITEM 15.45.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.45.1 (Dismantling C.I. pipes including excavation and refilling trenches after taking out the pipes, manually/ by mechanical means breaking lead caulked joints, melting of lead and making into blocks including stacking of pipes & lead at site within 50 metre lead as per direction of Engineer-in-charge: Up to 150 mm diameter) is derived from 7 priced inputs for 40.26 metre and works out to ₹332.40 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Earth work in excavation for dismantling pipes
  • including refilling of excavated earth
  • 1x40.26x0.55x0.75 m =16.61cum
  • =1x40.26x(22/7)/4x(0.118)x(0.118) =0.44cum
  • Total =16.17cum
  • Deduct for pipes of average 100 mm dia
ANALYSIS OF RATES · ITEM 15.45.1DETAIL OF COST FOR 40.26 METRE OR 11 NOS JOINTS
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per Item No.2.8.1 of SH: EARTH WORKRate as per item 2.8.1cum16.17260.304,209.05
SUBRate as per Item No.2.25 of SH: EARTH WORKRate as per item 2.25cum16.17196.003,169.32
0761MATFuel woodquintal0.46550.00253.00
0771MATKerosene oillitre0.3850.0019.00
0117LABAssistant Fitter or 2nd class Fitterday0.63816.00514.08
0114LABBeldarday4.5736.003,312.00
9977MATCarriageL.S.53.822.27122.17
BUILD-UP TO RATE
TOTAL
11,598.62
Add 1 % Water charges on “W-A”
+42.20
TOTAL
11,640.82
Add GST on “X-A” (multiplying factor 0.2127)
+906.62
TOTAL
12,547.44
Add 15% CPOH on “Y-A”
+775.36
TOTAL
13,322.80
Add Cess @ 1% on “Z-A”
+59.44
Cost of 40.26 metre
13,382.24
Cost of 1.00 metre
332.40
SAY
₹332.40
D-02/SOURCEPRINTED PAGE 1128
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1128

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1128. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSDISMANTLING AND DEMOLISHING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.