Dismantling C.I. pipes including excavation and refilling trenches after taking out the pipes, manually/ by mechanical means breaking lead caulked joints, melting of lead and making into blocks including stacking of pipes & lead at site within 50 metre lead as per direction of Engineer-in-charge

Above 150 mm dia up to 300 mm dia
Item number
15.45.2
Analysis basis
40.26 metre
Priced inputs
7
Derived rate
₹456.65/ METRE
D-01/RATE ANALYSISITEM 15.45.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.45.2 (Dismantling C.I. pipes including excavation and refilling trenches after taking out the pipes, manually/ by mechanical means breaking lead caulked joints, melting of lead and making into blocks including stacking of pipes & lead at site within 50 metre lead as per direction of Engineer-in-charge: Above 150 mm dia up to 300 mm dia) is derived from 7 priced inputs for 40.26 metre and works out to ₹456.65 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Earth work in excavation for dismantling pipes
  • including refilling of excavated earth
  • 1x40.26x0.65x0.75 m =19.63cum
  • =1x40.26x(22/7)/4x(0.274)x(0.274) =2.37cum
  • Total =17.26cum
  • Deduct for pipes of average 250 mm dia
ANALYSIS OF RATES · ITEM 15.45.2DETAIL OF COST FOR 40.26 METRE OR 11 NOS JOINTS
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per Item No.2.8.1 of SH: EARTH WORKRate as per item 2.8.1cum17.26260.304,492.78
SUBRate as per Item No.2.25 of SH: EARTH WORKRate as per item 2.25cum17.26196.003,382.96
0761MATFuel woodquintal1.03550.00566.50
0771MATKerosene oillitre1.1450.0057.00
0117LABAssistant Fitter or 2nd class Fitterday1.3816.001,060.80
0114LABBeldarday7.5736.005,520.00
9977MATCarriageL.S.80.732.27183.26
BUILD-UP TO RATE
TOTAL
15,263.30
Add 1 % Water charges on “W-A”
+73.88
TOTAL
15,337.18
Add GST on “X-A” (multiplying factor 0.2127)
+1,587.05
TOTAL
16,924.23
Add 15% CPOH on “Y-A”
+1,357.27
TOTAL
18,281.50
Add Cess @ 1% on “Z-A”
+104.06
Cost of 40.26 metre
18,385.56
Cost of 1.00 metre
456.67
SAY
₹456.65
D-02/SOURCEPRINTED PAGE 1129
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1129

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1129. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSDISMANTLING AND DEMOLISHING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.