CPWD Analysis of Rates · Dismantling and Demolishing
Dismantling C.I. pipes including excavation and refilling trenches after taking out the pipes, manually/ by mechanical means breaking lead caulked joints, melting of lead and making into blocks including stacking of pipes & lead at site within 50 metre lead as per direction of Engineer-in-charge
Above 150 mm dia up to 300 mm dia
- Item number
- 15.45.2
- Analysis basis
- Detail of cost for 40.26 metre or 11 nos joints
- Priced inputs
- 7
- Derived rate
- ₹456.65 / metre
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.45.2 — Dismantling C.I. pipes including excavation and refilling trenches after taking out the pipes, manually/ by mechanical means breaking lead caulked joints, melting of lead and making into blocks including stacking of pipes & lead at site within 50 metre lead as per direction of Engineer-in-charge: Above 150 mm dia up to 300 mm dia — is derived from 7 priced inputs for 40.26 metre and works out to ₹456.65 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- Earth work in excavation for dismantling pipes
- including refilling of excavated earth
- 1x40.26x0.65x0.75 m =19.63cum
- =1x40.26x(22/7)/4x(0.274)x(0.274) =2.37cum
- Total =17.26cum
- Deduct for pipes of average 250 mm dia
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| Rate as per Item No.2.8.1 of SH: EARTH WORKRate as per item 2.8.1Sub-analysis | cum | 17.26 | 260.30 | 4,492.78 | |
| Rate as per Item No.2.25 of SH: EARTH WORKRate as per item 2.25Sub-analysis | cum | 17.26 | 196.00 | 3,382.96 | |
| 0761 | Fuel woodMaterial | quintal | 1.03 | 550.00 | 566.50 |
| 0771 | Kerosene oilMaterial | litre | 1.14 | 50.00 | 57.00 |
| 0117 | Assistant Fitter or 2nd class FitterLabour | day | 1.3 | 816.00 | 1,060.80 |
| 0114 | BeldarLabour | day | 7.5 | 736.00 | 5,520.00 |
| 9977 | CarriageMaterial | L.S. | 80.73 | 2.27 | 183.26 |
- TOTAL
- 15,263.30
- Add 1 % Water charges on “W-A”
- 73.88
- TOTAL
- 15,337.18
- Add GST on “X-A” (multiplying factor 0.2127)
- 1,587.05
- TOTAL
- 16,924.23
- Add 15% CPOH on “Y-A”
- 1,357.27
- TOTAL
- 18,281.50
- Add Cess @ 1% on “Z-A”
- 104.06
- Cost of 40.26 metre
- 18,385.56
- Cost of 1.00 metre
- 456.67
- Say
- 456.65
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1129. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.