Dismantling C.I. pipes including excavation and refilling trenches after taking out the pipes, manually/ by mechanical means breaking lead caulked joints, melting of lead and making into blocks including stacking of pipes & lead at site within 50 metre lead as per direction of Engineer-in-charge
- Item number
- 15.45.3
- Analysis basis
- 40.26 metre
- Priced inputs
- 7
- Derived rate
- ₹614.30/ METRE
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.45.3 (Dismantling C.I. pipes including excavation and refilling trenches after taking out the pipes, manually/ by mechanical means breaking lead caulked joints, melting of lead and making into blocks including stacking of pipes & lead at site within 50 metre lead as per direction of Engineer-in-charge: Above 300 mm diameter) is derived from 7 priced inputs for 40.26 metre and works out to ₹614.30 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- Earth work in excavation for dismantling pipes
- including refilling of excavated earth
- 1x40.26x0.85x0.75 m =25.67cum
- =1x40.26x(22/7)/4x(0.48)x(0.48) =7.29cum
- Total =18.38cum
- Deduct for pipes of average 450 mm dia
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| SUB | Rate as per Item No.2.8.1 of SH: EARTH WORKRate as per item 2.8.1 | cum | 18.38 | 260.30 | 4,784.31 | |
| SUB | Rate as per Item No.2.25 of SH: EARTH WORKRate as per item 2.25 | cum | 18.38 | 196.00 | 3,602.48 | |
| 0761 | MAT | Fuel wood | quintal | 1.4 | 550.00 | 770.00 |
| 0771 | MAT | Kerosene oil | litre | 2.27 | 50.00 | 113.50 |
| 0117 | LAB | Assistant Fitter or 2nd class Fitter | day | 2.25 | 816.00 | 1,836.00 |
| 0114 | LAB | Beldar | day | 11.5 | 736.00 | 8,464.00 |
| 9988 | MAT | Carriage and sundries | L.S. | 134.55 | 2.27 | 305.43 |
- TOTAL
- 19,875.72
- Add 1 % Water charges on “W-A”
- +114.89
- TOTAL
- 19,990.61
- Add GST on “X-A” (multiplying factor 0.2127)
- +2,468.13
- TOTAL
- 22,458.74
- Add 15% CPOH on “Y-A”
- +2,110.79
- TOTAL
- 24,569.53
- Add Cess @ 1% on “Z-A”
- +161.83
- Cost of 40.26 metre
- 24,731.36
- Cost of 1.00 metre
- 614.29
- SAY
- ₹614.30
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1130
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1130. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.