Skip to main content

CPWD Analysis of Rates · Dismantling and Demolishing

Dismantling C.I. pipes including excavation and refilling trenches after taking out the pipes, manually/ by mechanical means breaking lead caulked joints, melting of lead and making into blocks including stacking of pipes & lead at site within 50 metre lead as per direction of Engineer-in-charge

Above 300 mm diameter

Item number
15.45.3
Analysis basis
Detail of cost for 40.26 metre or 11 nos joints
Priced inputs
7
Derived rate
614.30 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.45.3 Dismantling C.I. pipes including excavation and refilling trenches after taking out the pipes, manually/ by mechanical means breaking lead caulked joints, melting of lead and making into blocks including stacking of pipes & lead at site within 50 metre lead as per direction of Engineer-in-charge: Above 300 mm diameter — is derived from 7 priced inputs for 40.26 metre and works out to ₹614.30 per metre after water charges, GST, CPOH and cess. The full build-up is below.

  • Earth work in excavation for dismantling pipes
  • including refilling of excavated earth
  • 1x40.26x0.85x0.75 m =25.67cum
  • =1x40.26x(22/7)/4x(0.48)x(0.48) =7.29cum
  • Total =18.38cum
  • Deduct for pipes of average 450 mm dia
CodeInputUnitQuantityRate (INR)Amount (INR)
Rate as per Item No.2.8.1 of SH: EARTH WORKRate as per item 2.8.1Sub-analysiscum18.38260.304,784.31
Rate as per Item No.2.25 of SH: EARTH WORKRate as per item 2.25Sub-analysiscum18.38196.003,602.48
0761Fuel woodMaterialquintal1.4550.00770.00
0771Kerosene oilMateriallitre2.2750.00113.50
0117Assistant Fitter or 2nd class FitterLabourday2.25816.001,836.00
0114BeldarLabourday11.5736.008,464.00
9988Carriage and sundriesMaterialL.S.134.552.27305.43
TOTAL
19,875.72
Add 1 % Water charges on “W-A”
114.89
TOTAL
19,990.61
Add GST on “X-A” (multiplying factor 0.2127)
2,468.13
TOTAL
22,458.74
Add 15% CPOH on “Y-A”
2,110.79
TOTAL
24,569.53
Add Cess @ 1% on “Z-A”
161.83
Cost of 40.26 metre
24,731.36
Cost of 1.00 metre
614.29
Say
614.30

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1130. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works