Dismantling C.I. pipes including excavation and refilling trenches after taking out the pipes, manually/ by mechanical means breaking lead caulked joints, melting of lead and making into blocks including stacking of pipes & lead at site within 50 metre lead as per direction of Engineer-in-charge

Above 300 mm diameter
Item number
15.45.3
Analysis basis
40.26 metre
Priced inputs
7
Derived rate
₹614.30/ METRE
D-01/RATE ANALYSISITEM 15.45.3

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.45.3 (Dismantling C.I. pipes including excavation and refilling trenches after taking out the pipes, manually/ by mechanical means breaking lead caulked joints, melting of lead and making into blocks including stacking of pipes & lead at site within 50 metre lead as per direction of Engineer-in-charge: Above 300 mm diameter) is derived from 7 priced inputs for 40.26 metre and works out to ₹614.30 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Earth work in excavation for dismantling pipes
  • including refilling of excavated earth
  • 1x40.26x0.85x0.75 m =25.67cum
  • =1x40.26x(22/7)/4x(0.48)x(0.48) =7.29cum
  • Total =18.38cum
  • Deduct for pipes of average 450 mm dia
ANALYSIS OF RATES · ITEM 15.45.3DETAIL OF COST FOR 40.26 METRE OR 11 NOS JOINTS
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per Item No.2.8.1 of SH: EARTH WORKRate as per item 2.8.1cum18.38260.304,784.31
SUBRate as per Item No.2.25 of SH: EARTH WORKRate as per item 2.25cum18.38196.003,602.48
0761MATFuel woodquintal1.4550.00770.00
0771MATKerosene oillitre2.2750.00113.50
0117LABAssistant Fitter or 2nd class Fitterday2.25816.001,836.00
0114LABBeldarday11.5736.008,464.00
9988MATCarriage and sundriesL.S.134.552.27305.43
BUILD-UP TO RATE
TOTAL
19,875.72
Add 1 % Water charges on “W-A”
+114.89
TOTAL
19,990.61
Add GST on “X-A” (multiplying factor 0.2127)
+2,468.13
TOTAL
22,458.74
Add 15% CPOH on “Y-A”
+2,110.79
TOTAL
24,569.53
Add Cess @ 1% on “Z-A”
+161.83
Cost of 40.26 metre
24,731.36
Cost of 1.00 metre
614.29
SAY
₹614.30
D-02/SOURCEPRINTED PAGE 1130
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1130

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1130. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.