Dismantling steel cylinder R.C. pipes including excavation and refilling trenches after taking out the pipes, manually/ by mechanical means breaking lead caulked joints, melting of lead and making into blocks including stacking of pipes & lead at site within 50 metres lead as per direction of Engineer-in-charge
- Item number
- 15.46.1
- Analysis basis
- 40.26 metre
- Priced inputs
- 8
- Derived rate
- ₹695.25/ METRE
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.46.1 (Dismantling steel cylinder R.C. pipes including excavation and refilling trenches after taking out the pipes, manually/ by mechanical means breaking lead caulked joints, melting of lead and making into blocks including stacking of pipes & lead at site within 50 metres lead as per direction of Engineer-in-charge : Up to 600 mm diameter) is derived from 8 priced inputs for 40.26 metre and works out to ₹695.25 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- Earth work in excavation for dismantling pipes
- including refilling of excavated earth
- 1x40.26x1.30x1.65 m =86.36cum
- =1x40.26x(22/7)/4x(0.48)x(0.48) =7.29cum
- Total=79.07cum
- Deduct for pipes of average 450 mm dia
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0114 | LAB | Beldar | day | 5.32 | 736.00 | 3,915.52 |
| 0115 | LAB | Coolie | day | 5.46 | 736.00 | 4,018.56 |
| 0101 | LAB | Bhisti | day | 0.31 | 816.00 | 252.96 |
| 0761 | MAT | Fuel wood | quintal | 1.4 | 550.00 | 770.00 |
| 0771 | MAT | Kerosene oil | litre | 2.27 | 50.00 | 113.50 |
| 0117 | LAB | Assistant Fitter or 2nd class Fitter | day | 2.25 | 816.00 | 1,836.00 |
| 0114 | LAB | Beldar | day | 11.5 | 736.00 | 8,464.00 |
| 9988 | MAT | Carriage and sundries | L.S. | 134.55 | 2.27 | 305.43 |
- TOTAL
- 19,675.97
- Add 1 % Water charges on “W”
- +196.76
- TOTAL
- 19,872.73
- Add GST on “X” (multiplying factor 0.2127)
- +4,226.93
- TOTAL
- 24,099.66
- Add 15% CPOH on “Y”
- +3,614.95
- TOTAL
- 27,714.61
- Add Cess @ 1% on “Z”
- +277.15
- Cost of 40.26 metre
- 27,991.76
- Cost of 1.00 metre
- 695.27
- SAY
- ₹695.25
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1130
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1130. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.