Dismantling steel cylinder R.C. pipes including excavation and refilling trenches after taking out the pipes, manually/ by mechanical means breaking lead caulked joints, melting of lead and making into blocks including stacking of pipes & lead at site within 50 metres lead as per direction of Engineer-in-charge
- Item number
- 15.46.2
- Analysis basis
- 40.26 metre
- Priced inputs
- 8
- Derived rate
- ₹1,752.45/ METRE
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.46.2 (Dismantling steel cylinder R.C. pipes including excavation and refilling trenches after taking out the pipes, manually/ by mechanical means breaking lead caulked joints, melting of lead and making into blocks including stacking of pipes & lead at site within 50 metres lead as per direction of Engineer-in-charge : Above 600 mm diameter) is derived from 8 priced inputs for 40.26 metre and works out to ₹1,752.45 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- Earth work in excavation for dismantling pipes
- including refilling of excavated earth
- 1x40.26x1.30x1.65 m =86.36cum
- =1x40.26x(22/7)/4x(1.00)x(1.00) =31.63cum
- Total=54.73cum
- Deduct for pipes of average 900 mm dia
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0114 | LAB | Beldar | day | 15.82 | 736.00 | 11,643.52 |
| 0115 | LAB | Coolie | day | 16.25 | 736.00 | 11,960.00 |
| 0101 | LAB | Bhisti | day | 0.93 | 816.00 | 758.88 |
| 0761 | MAT | Fuel wood | quintal | 3.08 | 550.00 | 1,694.00 |
| 0771 | MAT | Kerosene oil | litre | 5 | 50.00 | 250.00 |
| 0117 | LAB | Assistant Fitter or 2nd class Fitter | day | 10 | 816.00 | 8,160.00 |
| 0114 | LAB | Beldar | day | 20 | 736.00 | 14,720.00 |
| 9988 | MAT | Carriage and sundries | L.S. | 179.4 | 2.27 | 407.24 |
- TOTAL
- 49,593.64
- Add 1 % Water charges on “W”
- +495.94
- TOTAL
- 50,089.58
- Add GST on “X” (multiplying factor 0.2127)
- +10,654.05
- TOTAL
- 60,743.63
- Add 15% CPOH on “Y”
- +9,111.54
- TOTAL
- 69,855.17
- Add Cess @ 1% on “Z”
- +698.55
- Cost of 40.26 metre
- 70,553.72
- Cost of 1.00 metre
- 1,752.45
- SAY
- ₹1,752.45
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1131
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1131. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.