Skip to main content

Dismantling steel cylinder R.C. pipes including excavation and refilling trenches after taking out the pipes, manually/ by mechanical means breaking lead caulked joints, melting of lead and making into blocks including stacking of pipes & lead at site within 50 metres lead as per direction of Engineer-in-charge

Above 600 mm diameter
Item number
15.46.2
Analysis basis
40.26 metre
Priced inputs
8
Derived rate
₹1,752.45/ METRE
D-01/RATE ANALYSISITEM 15.46.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.46.2 (Dismantling steel cylinder R.C. pipes including excavation and refilling trenches after taking out the pipes, manually/ by mechanical means breaking lead caulked joints, melting of lead and making into blocks including stacking of pipes & lead at site within 50 metres lead as per direction of Engineer-in-charge : Above 600 mm diameter) is derived from 8 priced inputs for 40.26 metre and works out to ₹1,752.45 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Earth work in excavation for dismantling pipes
  • including refilling of excavated earth
  • 1x40.26x1.30x1.65 m =86.36cum
  • =1x40.26x(22/7)/4x(1.00)x(1.00) =31.63cum
  • Total=54.73cum
  • Deduct for pipes of average 900 mm dia
ANALYSIS OF RATES · ITEM 15.46.2DETAIL OF COST FOR 40.26 METRE OR 11 NOS JOINTS
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0114LABBeldarday15.82736.0011,643.52
0115LABCoolieday16.25736.0011,960.00
0101LABBhistiday0.93816.00758.88
0761MATFuel woodquintal3.08550.001,694.00
0771MATKerosene oillitre550.00250.00
0117LABAssistant Fitter or 2nd class Fitterday10816.008,160.00
0114LABBeldarday20736.0014,720.00
9988MATCarriage and sundriesL.S.179.42.27407.24
BUILD-UP TO RATE
TOTAL
49,593.64
Add 1 % Water charges on “W”
+495.94
TOTAL
50,089.58
Add GST on “X” (multiplying factor 0.2127)
+10,654.05
TOTAL
60,743.63
Add 15% CPOH on “Y”
+9,111.54
TOTAL
69,855.17
Add Cess @ 1% on “Z”
+698.55
Cost of 40.26 metre
70,553.72
Cost of 1.00 metre
1,752.45
SAY
₹1,752.45
D-02/SOURCEPRINTED PAGE 1131
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1131

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1131. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSDISMANTLING AND DEMOLISHING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.