Skip to main content

CPWD Analysis of Rates · Dismantling and Demolishing

Dismantling steel cylinder R.C. pipes including excavation and refilling trenches after taking out the pipes, manually/ by mechanical means breaking lead caulked joints, melting of lead and making into blocks including stacking of pipes & lead at site within 50 metres lead as per direction of Engineer-in-charge

Above 600 mm diameter

Item number
15.46.2
Analysis basis
Detail of cost for 40.26 metre or 11 nos joints
Priced inputs
8
Derived rate
1,752.45 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.46.2 Dismantling steel cylinder R.C. pipes including excavation and refilling trenches after taking out the pipes, manually/ by mechanical means breaking lead caulked joints, melting of lead and making into blocks including stacking of pipes & lead at site within 50 metres lead as per direction of Engineer-in-charge : Above 600 mm diameter — is derived from 8 priced inputs for 40.26 metre and works out to ₹1,752.45 per metre after water charges, GST, CPOH and cess. The full build-up is below.

  • Earth work in excavation for dismantling pipes
  • including refilling of excavated earth
  • 1x40.26x1.30x1.65 m =86.36cum
  • =1x40.26x(22/7)/4x(1.00)x(1.00) =31.63cum
  • Total=54.73cum
  • Deduct for pipes of average 900 mm dia
CodeInputUnitQuantityRate (INR)Amount (INR)
0114BeldarLabourday15.82736.0011,643.52
0115CoolieLabourday16.25736.0011,960.00
0101BhistiLabourday0.93816.00758.88
0761Fuel woodMaterialquintal3.08550.001,694.00
0771Kerosene oilMateriallitre550.00250.00
0117Assistant Fitter or 2nd class FitterLabourday10816.008,160.00
0114BeldarLabourday20736.0014,720.00
9988Carriage and sundriesMaterialL.S.179.42.27407.24
TOTAL
49,593.64
Add 1 % Water charges on “W”
495.94
TOTAL
50,089.58
Add GST on “X” (multiplying factor 0.2127)
10,654.05
TOTAL
60,743.63
Add 15% CPOH on “Y”
9,111.54
TOTAL
69,855.17
Add Cess @ 1% on “Z”
698.55
Cost of 40.26 metre
70,553.72
Cost of 1.00 metre
1,752.45
Say
1,752.45

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1131. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works