Dismantling asbestos cement pressure pipes including excavation and refilling trenches after taking out the pipes manually/ by mechanical means and stacking the pipes within 50 metres lead as per direction of Engineer-in-charge
- Item number
- 15.47.1
- Analysis basis
- 10 metre
- Priced inputs
- 6
- Derived rate
- ₹332.15/ METRE
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.47.1 (Dismantling asbestos cement pressure pipes including excavation and refilling trenches after taking out the pipes manually/ by mechanical means and stacking the pipes within 50 metres lead as per direction of Engineer-in-charge : Up to 150 mm diameter) is derived from 6 priced inputs for 10 metre and works out to ₹332.15 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- Earth work in excavation for dismantling pipes
- including refilling of excavated earth
- 10.00x0.55x0.75 m =4.125cum
- =1x10x(22/7)/4x(0.118)x(0.118) =0.109cum
- Total=4.016cum
- Deduct for pipes of average 100 mm dia
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0114 | LAB | Beldar | day | 1.16 | 736.00 | 853.76 |
| 0115 | LAB | Coolie | day | 1.19 | 736.00 | 875.84 |
| 0101 | LAB | Bhisti | day | 0.07 | 816.00 | 57.12 |
| 0114 | LAB | Beldar | day | 0.36 | 736.00 | 264.96 |
| 0115 | LAB | Coolie | day | 0.38 | 736.00 | 279.68 |
| 9988 | MAT | Carriage and sundries | L.S. | 1.56 | 2.27 | 3.54 |
- TOTAL
- 2,334.90
- Add 1 % Water charges on “W”
- +23.35
- TOTAL
- 2,358.25
- Add GST on “X” (multiplying factor 0.2127)
- +501.60
- TOTAL
- 2,859.85
- Add 15% CPOH on “Y”
- +428.98
- TOTAL
- 3,288.83
- Add Cess @ 1% on “Z”
- +32.89
- Cost of 10.00 metre
- 3,321.72
- Cost of 1.00 metre
- 332.17
- SAY
- ₹332.15
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1132
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1132. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.