CPWD Analysis of Rates · Dismantling and Demolishing
Dismantling asbestos cement pressure pipes including excavation and refilling trenches after taking out the pipes manually/ by mechanical means and stacking the pipes within 50 metres lead as per direction of Engineer-in-charge
Up to 150 mm diameter
- Item number
- 15.47.1
- Analysis basis
- Detail of cost for 10 metre or 11 nos joints
- Priced inputs
- 6
- Derived rate
- ₹332.15 / metre
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.47.1 — Dismantling asbestos cement pressure pipes including excavation and refilling trenches after taking out the pipes manually/ by mechanical means and stacking the pipes within 50 metres lead as per direction of Engineer-in-charge : Up to 150 mm diameter — is derived from 6 priced inputs for 10 metre and works out to ₹332.15 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- Earth work in excavation for dismantling pipes
- including refilling of excavated earth
- 10.00x0.55x0.75 m =4.125cum
- =1x10x(22/7)/4x(0.118)x(0.118) =0.109cum
- Total=4.016cum
- Deduct for pipes of average 100 mm dia
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0114 | BeldarLabour | day | 1.16 | 736.00 | 853.76 |
| 0115 | CoolieLabour | day | 1.19 | 736.00 | 875.84 |
| 0101 | BhistiLabour | day | 0.07 | 816.00 | 57.12 |
| 0114 | BeldarLabour | day | 0.36 | 736.00 | 264.96 |
| 0115 | CoolieLabour | day | 0.38 | 736.00 | 279.68 |
| 9988 | Carriage and sundriesMaterial | L.S. | 1.56 | 2.27 | 3.54 |
- TOTAL
- 2,334.90
- Add 1 % Water charges on “W”
- 23.35
- TOTAL
- 2,358.25
- Add GST on “X” (multiplying factor 0.2127)
- 501.60
- TOTAL
- 2,859.85
- Add 15% CPOH on “Y”
- 428.98
- TOTAL
- 3,288.83
- Add Cess @ 1% on “Z”
- 32.89
- Cost of 10.00 metre
- 3,321.72
- Cost of 1.00 metre
- 332.17
- Say
- 332.15
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1132. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.