Dismantling asbestos cement pressure pipes including excavation and refilling trenches after taking out the pipes manually/ by mechanical means and stacking the pipes within 50 metres lead as per direction of Engineer-in-charge

Up to 150 mm diameter
Item number
15.47.1
Analysis basis
10 metre
Priced inputs
6
Derived rate
₹332.15/ METRE
D-01/RATE ANALYSISITEM 15.47.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.47.1 (Dismantling asbestos cement pressure pipes including excavation and refilling trenches after taking out the pipes manually/ by mechanical means and stacking the pipes within 50 metres lead as per direction of Engineer-in-charge : Up to 150 mm diameter) is derived from 6 priced inputs for 10 metre and works out to ₹332.15 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Earth work in excavation for dismantling pipes
  • including refilling of excavated earth
  • 10.00x0.55x0.75 m =4.125cum
  • =1x10x(22/7)/4x(0.118)x(0.118) =0.109cum
  • Total=4.016cum
  • Deduct for pipes of average 100 mm dia
ANALYSIS OF RATES · ITEM 15.47.1DETAIL OF COST FOR 10 METRE OR 11 NOS JOINTS
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0114LABBeldarday1.16736.00853.76
0115LABCoolieday1.19736.00875.84
0101LABBhistiday0.07816.0057.12
0114LABBeldarday0.36736.00264.96
0115LABCoolieday0.38736.00279.68
9988MATCarriage and sundriesL.S.1.562.273.54
BUILD-UP TO RATE
TOTAL
2,334.90
Add 1 % Water charges on “W”
+23.35
TOTAL
2,358.25
Add GST on “X” (multiplying factor 0.2127)
+501.60
TOTAL
2,859.85
Add 15% CPOH on “Y”
+428.98
TOTAL
3,288.83
Add Cess @ 1% on “Z”
+32.89
Cost of 10.00 metre
3,321.72
Cost of 1.00 metre
332.17
SAY
₹332.15
D-02/SOURCEPRINTED PAGE 1132
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1132

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1132. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSDISMANTLING AND DEMOLISHING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.