CPWD Analysis of Rates · Dismantling and Demolishing
Dismantling C.I. or asbestos rain water pipe with fittings and clamps including stacking the material within 50 metres lead
100 mm dia pipe
- Item number
- 15.42.2
- Analysis basis
- Detail of cost for 10 metre
- Priced inputs
- 3
- Derived rate
- ₹78.00 / metre
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.42.2 — Dismantling C.I. or asbestos rain water pipe with fittings and clamps including stacking the material within 50 metres lead : 100 mm dia pipe — is derived from 3 priced inputs for 10 metre and works out to ₹78.00 per metre after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0114 | BeldarLabour | day | 0.36 | 736.00 | 264.96 |
| 0115 | CoolieLabour | day | 0.38 | 736.00 | 279.68 |
| 9999 | SundriesMaterial | L.S. | 1.56 | 2.27 | 3.54 |
- TOTAL
- 548.18
- Add 1 % Water charges on “W”
- 5.48
- TOTAL
- 553.66
- Add GST on “X” (multiplying factor 0.2127)
- 117.76
- TOTAL
- 671.42
- Add 15% CPOH on “Y”
- 100.71
- TOTAL
- 772.13
- Add Cess @ 1% on “Z”
- 7.72
- Cost of 10.00 metre
- 779.85
- Cost of 1.00 metre
- 77.99
- Say
- 78.00
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1125. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.