Skip to main content

Removing mortar from bricks and cleaning bricks including stacking within a lead of 50 m (stacks of cleaned bricks shall be measured)

From brick work in mud mortar
Item number
15.8.1
Analysis basis
1000 Nos
Priced inputs
4
Derived rate
₹4,658.45/ NOS
D-01/RATE ANALYSISITEM 15.8.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.8.1 (Removing mortar from bricks and cleaning bricks including stacking within a lead of 50 m (stacks of cleaned bricks shall be measured): From brick work in mud mortar) is derived from 4 priced inputs for 1000 Nos and works out to ₹4,658.45 each after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 15.8.1DETAIL OF COST FOR 1000 NOS
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0114LABBeldarday2.4736.001,766.40
0115LABCoolieday1.6736.001,177.60
0124LABMason 2nd classMason 2nd classday0.4816.00326.40
9999MATSundriesL.S.1.822.274.13
BUILD-UP TO RATE
TOTAL
3,274.53
Add 1 % Water charges on “W”
+32.75
TOTAL
3,307.28
Add GST on “X” (multiplying factor 0.2127)
+703.46
TOTAL
4,010.74
Add 15% CPOH on “Y”
+601.61
TOTAL
4,612.35
Add Cess @ 1% on “Z”
+46.12
Cost of 1000 Nos
4,658.47
SAY
₹4,658.45
D-02/SOURCEPRINTED PAGE 1103
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1103

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1103. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSDISMANTLING AND DEMOLISHING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.