Skip to main content

CPWD Analysis of Rates · Dismantling and Demolishing

Removing mortar from bricks and cleaning bricks including stacking within a lead of 50 m (stacks of cleaned bricks shall be measured)

From brick work in mud mortar

Item number
15.8.1
Analysis basis
Detail of cost for 1000 Nos
Priced inputs
4
Derived rate
4,658.45 / Nos

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.8.1 Removing mortar from bricks and cleaning bricks including stacking within a lead of 50 m (stacks of cleaned bricks shall be measured): From brick work in mud mortar — is derived from 4 priced inputs for 1000 Nos and works out to ₹4,658.45 each after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
0114BeldarLabourday2.4736.001,766.40
0115CoolieLabourday1.6736.001,177.60
0124Mason 2nd classMason 2nd classLabourday0.4816.00326.40
9999SundriesMaterialL.S.1.822.274.13
TOTAL
3,274.53
Add 1 % Water charges on “W”
32.75
TOTAL
3,307.28
Add GST on “X” (multiplying factor 0.2127)
703.46
TOTAL
4,010.74
Add 15% CPOH on “Y”
601.61
TOTAL
4,612.35
Add Cess @ 1% on “Z”
46.12
Cost of 1000 Nos
4,658.47
Say
4,658.45

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1103. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works