CPWD Analysis of Rates · Dismantling and Demolishing
Removing mortar from bricks and cleaning bricks including stacking within a lead of 50 m (stacks of cleaned bricks shall be measured)
From brick work in mud mortar
- Item number
- 15.8.1
- Analysis basis
- Detail of cost for 1000 Nos
- Priced inputs
- 4
- Derived rate
- ₹4,658.45 / Nos
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.8.1 — Removing mortar from bricks and cleaning bricks including stacking within a lead of 50 m (stacks of cleaned bricks shall be measured): From brick work in mud mortar — is derived from 4 priced inputs for 1000 Nos and works out to ₹4,658.45 each after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0114 | BeldarLabour | day | 2.4 | 736.00 | 1,766.40 |
| 0115 | CoolieLabour | day | 1.6 | 736.00 | 1,177.60 |
| 0124 | Mason 2nd classMason 2nd classLabour | day | 0.4 | 816.00 | 326.40 |
| 9999 | SundriesMaterial | L.S. | 1.82 | 2.27 | 4.13 |
- TOTAL
- 3,274.53
- Add 1 % Water charges on “W”
- 32.75
- TOTAL
- 3,307.28
- Add GST on “X” (multiplying factor 0.2127)
- 703.46
- TOTAL
- 4,010.74
- Add 15% CPOH on “Y”
- 601.61
- TOTAL
- 4,612.35
- Add Cess @ 1% on “Z”
- 46.12
- Cost of 1000 Nos
- 4,658.47
- Say
- 4,658.45
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1103. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.