Demolishing brick work manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge

In cement mortar
Item number
15.7.4
Analysis basis
1 cum
Priced inputs
3
Derived rate
₹2,060.20/ CUM
D-01/RATE ANALYSISITEM 15.7.4

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.7.4 (Demolishing brick work manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge In cement mortar) is derived from 3 priced inputs for 1 cum and works out to ₹2,060.20 per cum after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 15.7.4DETAIL OF COST FOR 1 CUM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0114LABBeldarday1.06736.00780.16
0115LABCoolieday0.9736.00662.40
9999MATSundriesL.S.2.472.275.61
BUILD-UP TO RATE
TOTAL
1,448.17
Add 1 % Water charges on “W”
+14.48
TOTAL
1,462.65
Add GST on “X” (multiplying factor 0.2127)
+311.11
TOTAL
1,773.76
Add 15% CPOH on “Y”
+266.06
TOTAL
2,039.82
Add Cess @ 1% on “Z”
+20.40
Cost of 1.00 cum
2,060.22
SAY
₹2,060.20
D-02/SOURCEPRINTED PAGE 1103
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1103

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1103. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSDISMANTLING AND DEMOLISHING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.