Dismantling aluminium/ Gypsum partitions, doors, windows, fixed glazing and false ceiling including disposal of unserviceable material and stacking of serviceable material with in 50 meters lead as directed by Engineer-in-charge

Item number
15.57
Analysis basis
10 sqm
Priced inputs
3
Derived rate
₹56.35/ SQM
D-01/RATE ANALYSISITEM 15.57

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.57 (Dismantling aluminium/ Gypsum partitions, doors, windows, fixed glazing and false ceiling including disposal of unserviceable material and stacking of serviceable material with in 50 meters lead as directed by Engineer-in-charge) is derived from 3 priced inputs for 10 sqm and works out to ₹56.35 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 15.57DETAIL OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0112LABCarpenter 2nd classday0.2816.00163.20
0114LABBeldarday0.3736.00220.80
9999MATSundriesL.S.5.382.2712.21
BUILD-UP TO RATE
TOTAL
396.21
Add 1 % Water charges on “W”
+3.96
TOTAL
400.17
Add GST on “X” (multiplying factor 0.2127)
+85.12
TOTAL
485.29
Add 15% CPOH on “Y”
+72.79
TOTAL
558.08
Add Cess @ 1% on “Z”
+5.58
Cost of 10.00 sqm
563.66
Cost of 1.00 sqm
56.37
SAY
₹56.35
D-02/SOURCEPRINTED PAGE 1140
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1140

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1140. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSDISMANTLING AND DEMOLISHING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.