Dismantling old plaster or skirting raking out joints and cleaning the surface for plaster including disposal of rubbish to the dumping ground within 50 metres lead

Item number
15.56
Analysis basis
Detail of cost for 10 sqm
Priced inputs
4
Derived rate
54.65 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.56 Dismantling old plaster or skirting raking out joints and cleaning the surface for plaster including disposal of rubbish to the dumping ground within 50 metres lead — is derived from 4 priced inputs for 10 sqm and works out to ₹54.65 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
0114BeldarLabourday0.36736.00264.96
0115CoolieLabourday0.08736.0058.88
0101BhistiLabourday0.07816.0057.12
9999Sundries for scaffolding etcMaterialL.S.1.432.273.25
TOTAL
384.21
Add 1 % Water charges on “W”
3.84
TOTAL
388.05
Add GST on “X” (multiplying factor 0.2127)
82.54
TOTAL
470.59
Add 15% CPOH on “Y”
70.59
TOTAL
541.18
Add Cess @ 1% on “Z”
5.41
Cost of 10.00 sqm
546.59
Cost of 1.00 sqm
54.66
Say
54.65

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1140. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works