Dismantling of cement concrete platform along with curtain walls and base concrete etc. including stacking of useful materials near the site and disposal of unserviceable materials within 50 metres lead

320 x 120 cm (outside to outside)
Item number
15.55.3
Analysis basis
one platform
Priced inputs
9
Derived rate
₹2,396.95/ ONE PLATFORM
D-01/RATE ANALYSISITEM 15.55.3

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.55.3 (Dismantling of cement concrete platform along with curtain walls and base concrete etc. including stacking of useful materials near the site and disposal of unserviceable materials within 50 metres lead : 320 x 120 cm (outside to outside)) is derived from 9 priced inputs for one platform and works out to ₹2,396.95 per one platform after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Dismantling cement concrete 1:5:10
  • 8.00x0.35x0.12m =0.336cum
  • 2.80x0.80x0.075m =0.168cum
  • =0.504cum Say 0.50cum
  • Dismantling brick work in cement mortar
  • 8.00x0.20x0.30m =0.48cum
  • 8.40x0.10x0.20m =0.168cum
  • =0.648cum Say 0.65cum
  • Dismantling 40 mm C.C. flooring 1:2:4
  • 3.00x1.00x0.04m =0.12cum
ANALYSIS OF RATES · ITEM 15.55.3DETAIL OF COST FOR ONE PLATFORM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0114LABBeldarday0.44736.00323.84
0115LABCoolieday0.28736.00206.08
9999MATSundriesL.S.0.912.272.07
0114LABBeldarday0.69736.00507.84
0115LABCoolieday0.59736.00434.24
9999MATSundriesL.S.1.562.273.54
0114LABBeldarday0.19736.00139.84
0115LABCoolieday0.09736.0066.24
9999MATSundries for scaffolding etcL.S.0.522.271.18
BUILD-UP TO RATE
TOTAL
1,684.87
Add 1 % Water charges on “W”
+16.85
TOTAL
1,701.72
Add GST on “X” (multiplying factor 0.2127)
+361.96
TOTAL
2,063.68
Add 15% CPOH on “Y”
+309.55
TOTAL
2,373.23
Add Cess @ 1% on “Z”
+23.73
Cost of each
2,396.96
SAY
₹2,396.95
D-02/SOURCEPRINTED PAGE 1139
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1139

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1139. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSDISMANTLING AND DEMOLISHING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.