CPWD Analysis of Rates · Dismantling and Demolishing

Extra for dismantling trusses, rafters, purlins etc. of wood work for every additional span of one metre or part thereof beyond 10 metres

Of sectional area below 40 square centimetres

Item number
15.15.2
Analysis basis
Detail of cost for 10 metre for every additional
Priced inputs
3
Derived rate
1.65 / metre per metre span

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.15.2 Extra for dismantling trusses, rafters, purlins etc. of wood work for every additional span of one metre or part thereof beyond 10 metres : Of sectional area below 40 square centimetres — is derived from 3 priced inputs for 10 metre and works out to ₹1.65 per metre per metre span after water charges, GST, CPOH and cess. The full build-up is below.

  • span of 1 metre
CodeInputUnitQuantityRate (INR)Amount (INR)
0103Blacksmith 2nd classLabourday0.006816.004.90
0114BeldarLabourday0.008736.005.89
9999SundriesMaterialL.S.0.392.270.89
TOTAL
11.68
Add 1 % Water charges on “W”
0.12
TOTAL
11.80
Add GST on “X” (multiplying factor 0.2127)
2.51
TOTAL
14.31
Add 15% CPOH on “Y”
2.15
TOTAL
16.46
Add Cess @ 1% on “Z”
0.16
Cost of 10.00 metre per metre span
16.62
Cost of 1.00 metre per metre span
1.66
Say
1.65

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1110. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works