CPWD Analysis of Rates · Dismantling and Demolishing
Extra for dismantling trusses, rafters, purlins etc. of wood work for every additional span of one metre or part thereof beyond 10 metres
Of sectional area 40 square centimetres and above
- Item number
- 15.15.1
- Analysis basis
- Detail of cost for 1cum for every additional span
- Priced inputs
- 3
- Derived rate
- ₹589.55 / cum per metre span
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.15.1 — Extra for dismantling trusses, rafters, purlins etc. of wood work for every additional span of one metre or part thereof beyond 10 metres : Of sectional area 40 square centimetres and above — is derived from 3 priced inputs for 1cum for and works out to ₹589.55 per cum per metre span after water charges, GST, CPOH and cess. The full build-up is below.
- of 1 metre
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0103 | Blacksmith 2nd classLabour | day | 0.2 | 816.00 | 163.20 |
| 0114 | BeldarLabour | day | 0.3 | 736.00 | 220.80 |
| 9999 | SundriesMaterial | L.S. | 13.39 | 2.27 | 30.40 |
- TOTAL
- 414.40
- Add 1 % Water charges on “W”
- 4.14
- TOTAL
- 418.54
- Add GST on “X” (multiplying factor 0.2127)
- 89.02
- TOTAL
- 507.56
- Add 15% CPOH on “Y”
- 76.13
- TOTAL
- 583.69
- Add Cess @ 1% on “Z”
- 5.84
- Cost of 1.00 cum per metre span
- 589.53
- Say
- 589.55
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1109. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works