Skip to main content

CPWD Analysis of Rates · Dismantling and Demolishing

Extra for dismantling trusses, rafters, purlins etc. of wood work for every additional span of one metre or part thereof beyond 10 metres

Of sectional area 40 square centimetres and above

Item number
15.15.1
Analysis basis
Detail of cost for 1cum for every additional span
Priced inputs
3
Derived rate
589.55 / cum per metre span

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.15.1 Extra for dismantling trusses, rafters, purlins etc. of wood work for every additional span of one metre or part thereof beyond 10 metres : Of sectional area 40 square centimetres and above — is derived from 3 priced inputs for 1cum for and works out to ₹589.55 per cum per metre span after water charges, GST, CPOH and cess. The full build-up is below.

  • of 1 metre
CodeInputUnitQuantityRate (INR)Amount (INR)
0103Blacksmith 2nd classLabourday0.2816.00163.20
0114BeldarLabourday0.3736.00220.80
9999SundriesMaterialL.S.13.392.2730.40
TOTAL
414.40
Add 1 % Water charges on “W”
4.14
TOTAL
418.54
Add GST on “X” (multiplying factor 0.2127)
89.02
TOTAL
507.56
Add 15% CPOH on “Y”
76.13
TOTAL
583.69
Add Cess @ 1% on “Z”
5.84
Cost of 1.00 cum per metre span
589.53
Say
589.55

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1109. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works