CPWD Analysis of Rates · Dismantling and Demolishing

Dismantling wood work in frames, trusses, purlins and rafters up to 10 metres span and 5 metres height including stacking the material within 50 metres lead

Of sectional area below 40 square centimetres

Item number
15.14.2
Analysis basis
Detail of cost for 10 metre
Priced inputs
3
Derived rate
17.85 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.14.2 Dismantling wood work in frames, trusses, purlins and rafters up to 10 metres span and 5 metres height including stacking the material within 50 metres lead : Of sectional area below 40 square centimetres — is derived from 3 priced inputs for 10 metre and works out to ₹17.85 per metre after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
0112Carpenter 2nd classLabourday0.08816.0065.28
0114BeldarLabourday0.08736.0058.88
9999SundriesMaterialL.S.0.522.271.18
TOTAL
125.34
Add 1 % Water charges on “W”
1.25
TOTAL
126.59
Add GST on “X” (multiplying factor 0.2127)
26.93
TOTAL
153.52
Add 15% CPOH on “Y”
23.03
TOTAL
176.55
Add Cess @ 1% on “Z”
1.77
Cost of 10.00 metre
178.32
Cost of 1.00 metre
17.83
Say
17.85

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1109. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate