CPWD Analysis of Rates · Dismantling and Demolishing

Extra for dismantling trusses, rafters, purlins etc. of wood work for every additional height of one metre or part thereof beyond 5 metres

Of sectional area 40 square centimetres and above

Item number
15.16.1
Analysis basis
Detail of cost for 1 cum for every additional
Priced inputs
3
Derived rate
857.00 / cum per metre height

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.16.1 Extra for dismantling trusses, rafters, purlins etc. of wood work for every additional height of one metre or part thereof beyond 5 metres : Of sectional area 40 square centimetres and above — is derived from 3 priced inputs for 1 cum and works out to ₹857.00 per cum per metre height after water charges, GST, CPOH and cess. The full build-up is below.

  • height of 1 metre
CodeInputUnitQuantityRate (INR)Amount (INR)
0103Blacksmith 2nd classLabourday0.25816.00204.00
0114BeldarLabourday0.5736.00368.00
9999SundriesMaterialL.S.13.392.2730.40
TOTAL
602.40
Add 1 % Water charges on “W”
6.02
TOTAL
608.42
Add GST on “X” (multiplying factor 0.2127)
129.41
TOTAL
737.83
Add 15% CPOH on “Y”
110.67
TOTAL
848.50
Add Cess @ 1% on “Z”
8.49
Cost of 1.00 cum per metre height
856.99
Say
857.00

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1110. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.