CPWD Analysis of Rates · Dismantling and Demolishing

Dismantling tile work in floors and roofs laid in cement mortar including stacking material within 50 metres lead

For thickness of tiles 10 mm to 25 mm

Item number
15.23.1
Analysis basis
Detail of cost for 10 sqm
Priced inputs
4
Derived rate
73.40 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.23.1 Dismantling tile work in floors and roofs laid in cement mortar including stacking material within 50 metres lead For thickness of tiles 10 mm to 25 mm — is derived from 4 priced inputs for 10 sqm and works out to ₹73.40 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
0124Mason 2nd classMason 2nd classLabourday0.3816.00244.80
0114BeldarLabourday0.12736.0088.32
0115CoolieLabourday0.24736.00176.64
9999SundriesMaterialL.S.2.732.276.20
TOTAL
515.96
Add 1 % Water charges on “W”
5.16
TOTAL
521.12
Add GST on “X” (multiplying factor 0.2127)
110.84
TOTAL
631.96
Add 15% CPOH on “Y”
94.79
TOTAL
726.75
Add Cess @ 1% on “Z”
7.27
Cost of 10.00 sqm
734.02
Cost of 1.00 sqm
73.40
Say
73.40

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1114. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works