Dismantling tile work in floors and roofs laid in cement mortar including stacking material within 50 metres lead

For thickness of tiles above 25 mm and up to 40 mm
Item number
15.23.2
Analysis basis
10 sqm
Priced inputs
4
Derived rate
₹113.35/ SQM
D-01/RATE ANALYSISITEM 15.23.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.23.2 (Dismantling tile work in floors and roofs laid in cement mortar including stacking material within 50 metres lead For thickness of tiles above 25 mm and up to 40 mm) is derived from 4 priced inputs for 10 sqm and works out to ₹113.35 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 15.23.2DETAIL OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0124LABMason 2nd classMason 2nd classday0.59816.00481.44
0114LABBeldarday0.18736.00132.48
0115LABCoolieday0.24736.00176.64
9999MATSundriesL.S.2.732.276.20
BUILD-UP TO RATE
TOTAL
796.76
Add 1 % Water charges on “W”
+7.97
TOTAL
804.73
Add GST on “X” (multiplying factor 0.2127)
+171.17
TOTAL
975.90
Add 15% CPOH on “Y”
+146.39
TOTAL
1,122.29
Add Cess @ 1% on “Z”
+11.22
Cost of 10.00 sqm
1,133.51
Cost of 1.00 sqm
113.35
SAY
₹113.35
D-02/SOURCEPRINTED PAGE 1115
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1115

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1115. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSDISMANTLING AND DEMOLISHING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.