Demolishing dry brick pitching in floors, drains etc. including stacking of serviceable material and disposal of unserviceable material within 50 metres lead :

Item number
15.24
Analysis basis
1 cum
Priced inputs
3
Derived rate
₹1,317.65/ CUM
D-01/RATE ANALYSISITEM 15.24

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.24 (Demolishing dry brick pitching in floors, drains etc. including stacking of serviceable material and disposal of unserviceable material within 50 metres lead :) is derived from 3 priced inputs for 1 cum and works out to ₹1,317.65 per cum after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 15.24DETAIL OF COST FOR 1 CUM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0114LABBeldarday0.25736.00184.00
0115LABCoolieday1736.00736.00
9999MATSundriesL.S.2.732.276.20
BUILD-UP TO RATE
TOTAL
926.20
Add 1 % Water charges on “W”
+9.26
TOTAL
935.46
Add GST on “X” (multiplying factor 0.2127)
+198.97
TOTAL
1,134.43
Add 15% CPOH on “Y”
+170.16
TOTAL
1,304.59
Add Cess @ 1% on “Z”
+13.05
Cost of 1.00 cum
1,317.64
SAY
₹1,317.65
D-02/SOURCEPRINTED PAGE 1115
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1115

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1115. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.