Extra for marking of structural steel work required to be re-erected
- Item number
- 15.22
- Analysis basis
- 1 quintal
- Priced inputs
- 2
- Derived rate
- ₹4.65/ QUINTAL
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.22 (Extra for marking of structural steel work required to be re-erected) is derived from 2 priced inputs for 1 quintal and works out to ₹4.65 per quintal after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0130 | LAB | Mistry | day | 0.2 | 897.00 | 179.40 |
| 0114 | LAB | Beldar | day | 0.2 | 736.00 | 147.20 |
- TOTAL
- 326.60
- Add 1 % Water charges on “W”
- +3.27
- TOTAL
- 329.87
- Add GST on “X” (multiplying factor 0.2127)
- +70.16
- TOTAL
- 400.03
- Add 15% CPOH on “Y”
- +60.00
- TOTAL
- 460.03
- Add Cess @ 1% on “Z”
- +4.60
- Cost of 1.00 quintal
- 464.63
- Cost of 1.00 kg
- 4.65
- SAY
- ₹4.65
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1114
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1114. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.