CPWD Analysis of Rates · Dismantling and Demolishing

Extra for marking of structural steel work required to be re-erected

Item number
15.22
Analysis basis
Detail of cost for 1 quintal
Priced inputs
2
Derived rate
4.65 / quintal

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.22 Extra for marking of structural steel work required to be re-erected — is derived from 2 priced inputs for 1 quintal and works out to ₹4.65 per quintal after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
0130MistryLabourday0.2897.00179.40
0114BeldarLabourday0.2736.00147.20
TOTAL
326.60
Add 1 % Water charges on “W”
3.27
TOTAL
329.87
Add GST on “X” (multiplying factor 0.2127)
70.16
TOTAL
400.03
Add 15% CPOH on “Y”
60.00
TOTAL
460.03
Add Cess @ 1% on “Z”
4.60
Cost of 1.00 quintal
464.63
Cost of 1.00 kg
4.65
Say
4.65

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1114. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works