Extra for marking of structural steel work required to be re-erected

Item number
15.22
Analysis basis
1 quintal
Priced inputs
2
Derived rate
₹4.65/ QUINTAL
D-01/RATE ANALYSISITEM 15.22

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.22 (Extra for marking of structural steel work required to be re-erected) is derived from 2 priced inputs for 1 quintal and works out to ₹4.65 per quintal after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 15.22DETAIL OF COST FOR 1 QUINTAL
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0130LABMistryday0.2897.00179.40
0114LABBeldarday0.2736.00147.20
BUILD-UP TO RATE
TOTAL
326.60
Add 1 % Water charges on “W”
+3.27
TOTAL
329.87
Add GST on “X” (multiplying factor 0.2127)
+70.16
TOTAL
400.03
Add 15% CPOH on “Y”
+60.00
TOTAL
460.03
Add Cess @ 1% on “Z”
+4.60
Cost of 1.00 quintal
464.63
Cost of 1.00 kg
4.65
SAY
₹4.65
D-02/SOURCEPRINTED PAGE 1114
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1114

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1114. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.