Dismantling of cement concrete platform along with curtain walls and base concrete etc. including stacking of useful materials near the site and disposal of unserviceable materials within 50 metres lead
120 x 120 cm (outside to outside)
- Item number
- 15.55.1
- Analysis basis
- Detail of cost for one platform
- Priced inputs
- 9
- Derived rate
- ₹1,104.05 / one platform
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.55.1 — Dismantling of cement concrete platform along with curtain walls and base concrete etc. including stacking of useful materials near the site and disposal of unserviceable materials within 50 metres lead : 120 x 120 cm (outside to outside) — is derived from 9 priced inputs for one platform and works out to ₹1,104.05 per one platform after water charges, GST, CPOH and cess. The full build-up is below.
- Dismantling cement concrete 1:5:10
- 4.00x0.35x0.12m =0.168cum
- 0.80x0.80x0.075m =0.048cum
- =0.216cum Say 0.22cum
- Dismantling brick work in cement mortar
- 4.00x0.20x0.30m =0.24cum
- 4.00x0.10x0.20m =0.088cum
- =0.328cum Say 0.33cum
- Dismantling 40 mm C.C. flooring 1:2:4
- 1.00x1.00x0.04m =0.04cum
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0114 | BeldarLabour | day | 0.19 | 736.00 | 139.84 |
| 0115 | CoolieLabour | day | 0.12 | 736.00 | 88.32 |
| 9999 | SundriesMaterial | L.S. | 0.39 | 2.27 | 0.89 |
| 0114 | BeldarLabour | day | 0.35 | 736.00 | 257.60 |
| 0115 | CoolieLabour | day | 0.3 | 736.00 | 220.80 |
| 9999 | SundriesMaterial | L.S. | 0.91 | 2.27 | 2.07 |
| 0114 | BeldarLabour | day | 0.06 | 736.00 | 44.16 |
| 0115 | CoolieLabour | day | 0.03 | 736.00 | 22.08 |
| 9999 | Sundries for scaffolding etcMaterial | L.S. | 0.13 | 2.27 | 0.30 |
- TOTAL
- 776.06
- Add 1 % Water charges on “W”
- 7.76
- TOTAL
- 783.82
- Add GST on “X” (multiplying factor 0.2127)
- 166.72
- TOTAL
- 950.54
- Add 15% CPOH on “Y”
- 142.58
- TOTAL
- 1,093.12
- Add Cess @ 1% on “Z”
- 10.93
- Cost of each
- 1,104.05
- Say
- 1,104.05
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1137. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works