Dismantling steel work in built up sections in angles, tees, flats and channels including all gusset plates, bolts, nuts, cutting rivets, welding etc. including dismembering and stacking within 50 metres lead

Item number
15.18
Analysis basis
1 quintal
Priced inputs
4
Derived rate
₹5.65/ QUINTAL
D-01/RATE ANALYSISITEM 15.18

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.18 (Dismantling steel work in built up sections in angles, tees, flats and channels including all gusset plates, bolts, nuts, cutting rivets, welding etc. including dismembering and stacking within 50 metres lead) is derived from 4 priced inputs for 1 quintal and works out to ₹5.65 per quintal after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 15.18DETAIL OF COST FOR 1 QUINTAL
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0103LABBlacksmith 2nd classday0.15816.00122.40
0100LABBandhaniday0.1816.0081.60
0114LABBeldarday0.25736.00184.00
9999MATSundriesL.S.4.162.279.44
BUILD-UP TO RATE
TOTAL
397.44
Add 1 % Water charges on “W”
+3.97
TOTAL
401.41
Add GST on “X” (multiplying factor 0.2127)
+85.38
TOTAL
486.79
Add 15% CPOH on “Y”
+73.02
TOTAL
559.81
Add Cess @ 1% on “Z”
+5.60
Cost of 1.00 quintal
565.41
Cost of 1.00 kg
5.65
SAY
₹5.65
D-02/SOURCEPRINTED PAGE 1112
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1112

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1112. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.