CPWD Analysis of Rates · Dismantling and Demolishing

Dismantling steel work in built up sections in angles, tees, flats and channels including all gusset plates, bolts, nuts, cutting rivets, welding etc. including dismembering and stacking within 50 metres lead

Item number
15.18
Analysis basis
Detail of cost for 1 quintal
Priced inputs
4
Derived rate
5.65 / quintal

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.18 Dismantling steel work in built up sections in angles, tees, flats and channels including all gusset plates, bolts, nuts, cutting rivets, welding etc. including dismembering and stacking within 50 metres lead — is derived from 4 priced inputs for 1 quintal and works out to ₹5.65 per quintal after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
0103Blacksmith 2nd classLabourday0.15816.00122.40
0100BandhaniLabourday0.1816.0081.60
0114BeldarLabourday0.25736.00184.00
9999SundriesMaterialL.S.4.162.279.44
TOTAL
397.44
Add 1 % Water charges on “W”
3.97
TOTAL
401.41
Add GST on “X” (multiplying factor 0.2127)
85.38
TOTAL
486.79
Add 15% CPOH on “Y”
73.02
TOTAL
559.81
Add Cess @ 1% on “Z”
5.60
Cost of 1.00 quintal
565.41
Cost of 1.00 kg
5.65
Say
5.65

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1112. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.