Dismantling steel work in single sections including dismembering and stacking within 50 metres lead in

Channels, angles, tees and flats
Item number
15.17.2
Analysis basis
1 quintal
Priced inputs
4
Derived rate
₹2.30/ QUINTAL
D-01/RATE ANALYSISITEM 15.17.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.17.2 (Dismantling steel work in single sections including dismembering and stacking within 50 metres lead in: Channels, angles, tees and flats) is derived from 4 priced inputs for 1 quintal and works out to ₹2.30 per quintal after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 15.17.2DETAIL OF COST FOR 1 QUINTAL
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0103LABBlacksmith 2nd classday0.05816.0040.80
0100LABBandhaniday0.05816.0040.80
0114LABBeldarday0.1736.0073.60
9999MATSundriesL.S.2.732.276.20
BUILD-UP TO RATE
TOTAL
161.40
Add 1 % Water charges on “W”
+1.61
TOTAL
163.01
Add GST on “X” (multiplying factor 0.2127)
+34.67
TOTAL
197.68
Add 15% CPOH on “Y”
+29.65
TOTAL
227.33
Add Cess @ 1% on “Z”
+2.27
Cost of 1.00 quintal
229.60
Cost of 1.00 kg
2.30
SAY
₹2.30
D-02/SOURCEPRINTED PAGE 1112
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1112

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1112. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.