CPWD Analysis of Rates · Dismantling and Demolishing
Dismantling steel work in single sections including dismembering and stacking within 50 metres lead in
Channels, angles, tees and flats
- Item number
- 15.17.2
- Analysis basis
- Detail of cost for 1 quintal
- Priced inputs
- 4
- Derived rate
- ₹2.30 / quintal
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.17.2 — Dismantling steel work in single sections including dismembering and stacking within 50 metres lead in: Channels, angles, tees and flats — is derived from 4 priced inputs for 1 quintal and works out to ₹2.30 per quintal after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0103 | Blacksmith 2nd classLabour | day | 0.05 | 816.00 | 40.80 |
| 0100 | BandhaniLabour | day | 0.05 | 816.00 | 40.80 |
| 0114 | BeldarLabour | day | 0.1 | 736.00 | 73.60 |
| 9999 | SundriesMaterial | L.S. | 2.73 | 2.27 | 6.20 |
- TOTAL
- 161.40
- Add 1 % Water charges on “W”
- 1.61
- TOTAL
- 163.01
- Add GST on “X” (multiplying factor 0.2127)
- 34.67
- TOTAL
- 197.68
- Add 15% CPOH on “Y”
- 29.65
- TOTAL
- 227.33
- Add Cess @ 1% on “Z”
- 2.27
- Cost of 1.00 quintal
- 229.60
- Cost of 1.00 kg
- 2.30
- Say
- 2.30
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1112. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.