Dismantling steel work in single sections including dismembering and stacking within 50 metres lead in

R.S. Joists
Item number
15.17.1
Analysis basis
1 quintal
Priced inputs
4
Derived rate
₹3.40/ QUINTAL
D-01/RATE ANALYSISITEM 15.17.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.17.1 (Dismantling steel work in single sections including dismembering and stacking within 50 metres lead in: R.S. Joists) is derived from 4 priced inputs for 1 quintal and works out to ₹3.40 per quintal after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 15.17.1DETAIL OF COST FOR 1 QUINTAL
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0103LABBlacksmith 2nd classday0.05816.0040.80
0100LABBandhaniday0.1816.0081.60
0114LABBeldarday0.15736.00110.40
9999MATSundriesL.S.2.732.276.20
BUILD-UP TO RATE
TOTAL
239.00
Add 1 % Water charges on “W”
+2.39
TOTAL
241.39
Add GST on “X” (multiplying factor 0.2127)
+51.34
TOTAL
292.73
Add 15% CPOH on “Y”
+43.91
TOTAL
336.64
Add Cess @ 1% on “Z”
+3.37
Cost of 1.00 quintal
340.01
Cost of 1.00 kg
3.40
SAY
₹3.40
D-02/SOURCEPRINTED PAGE 1111
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1111

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1111. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.