Dismantling steel work manually/ by mechanical means in built up sections without dismembering and stacking within 50 metres lead as per direction of Engineer-in-charge
- Item number
- 15.19
- Analysis basis
- 1 quintal
- Priced inputs
- 3
- Derived rate
- ₹3.85/ QUINTAL
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.19 (Dismantling steel work manually/ by mechanical means in built up sections without dismembering and stacking within 50 metres lead as per direction of Engineer-in-charge) is derived from 3 priced inputs for 1 quintal and works out to ₹3.85 per quintal after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0100 | LAB | Bandhani | day | 0.1 | 816.00 | 81.60 |
| 0114 | LAB | Beldar | day | 0.25 | 736.00 | 184.00 |
| 9999 | MAT | Sundries | L.S. | 2.73 | 2.27 | 6.20 |
- TOTAL
- 271.80
- Add 1 % Water charges on “W”
- +2.72
- TOTAL
- 274.52
- Add GST on “X” (multiplying factor 0.2127)
- +58.39
- TOTAL
- 332.91
- Add 15% CPOH on “Y”
- +49.94
- TOTAL
- 382.85
- Add Cess @ 1% on “Z”
- +3.83
- Cost of 1.00 quintal
- 386.68
- Cost of 1.00 kg
- 3.87
- SAY
- ₹3.85
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1112
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1112. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.