CPWD Analysis of Rates · Dismantling and Demolishing
Extra for dismantling trusses, rafters, purlins etc. of steel work for every additional span of one metre or part thereof beyond 10 metres
- Item number
- 15.20
- Analysis basis
- Detail of cost for 1 quintal for every additional
- Priced inputs
- 3
- Derived rate
- ₹0.85 / quintal per metre span
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.20 — Extra for dismantling trusses, rafters, purlins etc. of steel work for every additional span of one metre or part thereof beyond 10 metres — is derived from 3 priced inputs for 1 quintal and works out to ₹0.85 per quintal per metre span after water charges, GST, CPOH and cess. The full build-up is below.
- span of 1 metre beyond 10 metre
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0100 | BandhaniLabour | day | 0.02 | 816.00 | 16.32 |
| 0114 | BeldarLabour | day | 0.06 | 736.00 | 44.16 |
| 9999 | SundriesMaterial | L.S. | 0.39 | 2.27 | 0.89 |
- TOTAL
- 61.37
- Add 1 % Water charges on “W”
- 0.61
- TOTAL
- 61.98
- Add GST on “X” (multiplying factor 0.2127)
- 13.18
- TOTAL
- 75.16
- Add 15% CPOH on “Y”
- 11.27
- TOTAL
- 86.43
- Add Cess @ 1% on “Z”
- 0.86
- Cost of 1.00 quintal per metre span
- 87.29
- Cost of 1.00 kg per metre span
- 0.87
- Say
- 0.85
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1113. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.