CPWD Analysis of Rates · Dismantling and Demolishing

Dismantling roofing including ridges, hips, valleys and gutters etc., and stacking the material within 50 metres lead of

Asbestos Cement sheet

Item number
15.28.2
Analysis basis
Detail of cost for 10 sqm
Priced inputs
3
Derived rate
77.30 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.28.2 Dismantling roofing including ridges, hips, valleys and gutters etc., and stacking the material within 50 metres lead of: Asbestos Cement sheet — is derived from 3 priced inputs for 10 sqm and works out to ₹77.30 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
0112Carpenter 2nd classLabourday0.2816.00163.20
0114BeldarLabourday0.5736.00368.00
9999SundriesMaterialL.S.5.332.2712.10
TOTAL
543.30
Add 1 % Water charges on “W”
5.43
TOTAL
548.73
Add GST on “X” (multiplying factor 0.2127)
116.71
TOTAL
665.44
Add 15% CPOH on “Y”
99.82
TOTAL
765.26
Add Cess @ 1% on “Z”
7.65
Cost of 10.00 sqm
772.91
Cost of 1.00 sqm
77.29
Say
77.30

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1117. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.