Dismantling roofing including ridges, hips, valleys and gutters etc., and stacking the material within 50 metres lead of
- Item number
- 15.28.2
- Analysis basis
- 10 sqm
- Priced inputs
- 3
- Derived rate
- ₹77.30/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.28.2 (Dismantling roofing including ridges, hips, valleys and gutters etc., and stacking the material within 50 metres lead of: Asbestos Cement sheet) is derived from 3 priced inputs for 10 sqm and works out to ₹77.30 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0112 | LAB | Carpenter 2nd class | day | 0.2 | 816.00 | 163.20 |
| 0114 | LAB | Beldar | day | 0.5 | 736.00 | 368.00 |
| 9999 | MAT | Sundries | L.S. | 5.33 | 2.27 | 12.10 |
- TOTAL
- 543.30
- Add 1 % Water charges on “W”
- +5.43
- TOTAL
- 548.73
- Add GST on “X” (multiplying factor 0.2127)
- +116.71
- TOTAL
- 665.44
- Add 15% CPOH on “Y”
- +99.82
- TOTAL
- 765.26
- Add Cess @ 1% on “Z”
- +7.65
- Cost of 10.00 sqm
- 772.91
- Cost of 1.00 sqm
- 77.29
- SAY
- ₹77.30
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1117
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1117. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.