Dismantling stone slab roofing over wooden karries or R.C.C. battens (dismantling karries and battens to be paid for separately), including stacking of serviceable material and disposal of unserviceable material within 50 metres lead

Item number
15.29
Analysis basis
1 cum
Priced inputs
3
Derived rate
₹2,664.65/ CUM
D-01/RATE ANALYSISITEM 15.29

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.29 (Dismantling stone slab roofing over wooden karries or R.C.C. battens (dismantling karries and battens to be paid for separately), including stacking of serviceable material and disposal of unserviceable material within 50 metres lead) is derived from 3 priced inputs for 1 cum and works out to ₹2,664.65 per cum after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 15.29DETAIL OF COST FOR 1 CUM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0114LABBeldarday1.77736.001,302.72
0115LABCoolieday0.75736.00552.00
9999MATSundriesL.S.8.062.2718.30
BUILD-UP TO RATE
TOTAL
1,873.02
Add 1 % Water charges on “W”
+18.73
TOTAL
1,891.75
Add GST on “X” (multiplying factor 0.2127)
+402.38
TOTAL
2,294.13
Add 15% CPOH on “Y”
+344.12
TOTAL
2,638.25
Add Cess @ 1% on “Z”
+26.38
Cost of 1.00 cum
2,664.63
SAY
₹2,664.65
D-02/SOURCEPRINTED PAGE 1117
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1117

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1117. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSDISMANTLING AND DEMOLISHING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.