Dismantling roofing including ridges, hips, valleys and gutters etc., and stacking the material within 50 metres lead of
- Item number
- 15.28.1
- Analysis basis
- 10 sqm
- Priced inputs
- 3
- Derived rate
- ₹164.95/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.28.1 (Dismantling roofing including ridges, hips, valleys and gutters etc., and stacking the material within 50 metres lead of: G.S. Sheet) is derived from 3 priced inputs for 10 sqm and works out to ₹164.95 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0112 | LAB | Carpenter 2nd class | day | 0.5 | 816.00 | 408.00 |
| 0114 | LAB | Beldar | day | 1 | 736.00 | 736.00 |
| 9999 | MAT | Sundries | L.S. | 6.76 | 2.27 | 15.35 |
- TOTAL
- 1,159.35
- Add 1 % Water charges on “W”
- +11.59
- TOTAL
- 1,170.94
- Add GST on “X” (multiplying factor 0.2127)
- +249.06
- TOTAL
- 1,420.00
- Add 15% CPOH on “Y”
- +213.00
- TOTAL
- 1,633.00
- Add Cess @ 1% on “Z”
- +16.33
- Cost of 10.00 sqm
- 1,649.33
- Cost of 1.00 sqm
- 164.93
- SAY
- ₹164.95
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1117
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1117. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.