Skip to main content

CPWD Analysis of Rates · Dismantling and Demolishing

Demolishing mud phaska in terracing and disposal of material within 50 metres lead

Item number
15.27
Analysis basis
Detail of cost for 1 cum
Priced inputs
3
Derived rate
914.30 / cum

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.27 Demolishing mud phaska in terracing and disposal of material within 50 metres lead — is derived from 3 priced inputs for 1 cum and works out to ₹914.30 per cum after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
0114BeldarLabourday0.25736.00184.00
0115CoolieLabourday0.62736.00456.32
9999SundriesMaterialL.S.1.042.272.36
TOTAL
642.68
Add 1 % Water charges on “W”
6.43
TOTAL
649.11
Add GST on “X” (multiplying factor 0.2127)
138.07
TOTAL
787.18
Add 15% CPOH on “Y”
118.08
TOTAL
905.26
Add Cess @ 1% on “Z”
9.05
Cost of 1.00 cum
914.31
Say
914.30

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1116. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works