Demolishing mud phaska in terracing and disposal of material within 50 metres lead

Item number
15.27
Analysis basis
1 cum
Priced inputs
3
Derived rate
₹914.30/ CUM
D-01/RATE ANALYSISITEM 15.27

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.27 (Demolishing mud phaska in terracing and disposal of material within 50 metres lead) is derived from 3 priced inputs for 1 cum and works out to ₹914.30 per cum after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 15.27DETAIL OF COST FOR 1 CUM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0114LABBeldarday0.25736.00184.00
0115LABCoolieday0.62736.00456.32
9999MATSundriesL.S.1.042.272.36
BUILD-UP TO RATE
TOTAL
642.68
Add 1 % Water charges on “W”
+6.43
TOTAL
649.11
Add GST on “X” (multiplying factor 0.2127)
+138.07
TOTAL
787.18
Add 15% CPOH on “Y”
+118.08
TOTAL
905.26
Add Cess @ 1% on “Z”
+9.05
Cost of 1.00 cum
914.31
SAY
₹914.30
D-02/SOURCEPRINTED PAGE 1116
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1116

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1116. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.