CPWD Analysis of Rates · Dismantling and Demolishing

Demolishing brick tile covering in terracing including stacking of serviceable material and disposal of unserviceable material within 50 metres lead

Item number
15.26
Analysis basis
Detail of cost for 10 sqm
Priced inputs
4
Derived rate
105.35 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.26 Demolishing brick tile covering in terracing including stacking of serviceable material and disposal of unserviceable material within 50 metres lead — is derived from 4 priced inputs for 10 sqm and works out to ₹105.35 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
0124Mason 2nd classMason 2nd classLabourday0.54816.00440.64
0114BeldarLabourday0.16736.00117.76
0115CoolieLabourday0.24736.00176.64
9999SundriesMaterialL.S.2.472.275.61
TOTAL
740.65
Add 1 % Water charges on “W”
7.41
TOTAL
748.06
Add GST on “X” (multiplying factor 0.2127)
159.11
TOTAL
907.17
Add 15% CPOH on “Y”
136.08
TOTAL
1,043.25
Add Cess @ 1% on “Z”
10.43
Cost of 10.00 sqm
1,053.68
Cost of 1.00 sqm
105.37
Say
105.35

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1116. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.