Dismantling cement asbestos or other hard board ceiling or partition walls including stacking of serviceable materials and disposal of unserviceable materials within 50 metres lead

Item number
15.41
Analysis basis
Detail of cost for 10 sqm.
Priced inputs
3
Derived rate
56.35 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.41 Dismantling cement asbestos or other hard board ceiling or partition walls including stacking of serviceable materials and disposal of unserviceable materials within 50 metres lead — is derived from 3 priced inputs for 10 sqm and works out to ₹56.35 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
0112Carpenter 2nd classLabourday0.2816.00163.20
0114BeldarLabourday0.3736.00220.80
9999SundriesMaterialL.S.5.332.2712.10
TOTAL
396.10
Add 1 % Water charges on “W”
3.96
TOTAL
400.06
Add GST on “X” (multiplying factor 0.2127)
85.09
TOTAL
485.15
Add 15% CPOH on “Y”
72.77
TOTAL
557.92
Add Cess @ 1% on “Z”
5.58
Cost of 10.00 sqm.
563.50
Cost of 1.00 sqm.
56.35
Say
56.35

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1124. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works