Dismantling cement asbestos or other hard board ceiling or partition walls including stacking of serviceable materials and disposal of unserviceable materials within 50 metres lead

Item number
15.41
Analysis basis
10 sqm
Priced inputs
3
Derived rate
₹56.35/ SQM
D-01/RATE ANALYSISITEM 15.41

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.41 (Dismantling cement asbestos or other hard board ceiling or partition walls including stacking of serviceable materials and disposal of unserviceable materials within 50 metres lead) is derived from 3 priced inputs for 10 sqm and works out to ₹56.35 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 15.41DETAIL OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0112LABCarpenter 2nd classday0.2816.00163.20
0114LABBeldarday0.3736.00220.80
9999MATSundriesL.S.5.332.2712.10
BUILD-UP TO RATE
TOTAL
396.10
Add 1 % Water charges on “W”
+3.96
TOTAL
400.06
Add GST on “X” (multiplying factor 0.2127)
+85.09
TOTAL
485.15
Add 15% CPOH on “Y”
+72.77
TOTAL
557.92
Add Cess @ 1% on “Z”
+5.58
Cost of 10.00 sqm.
563.50
Cost of 1.00 sqm.
56.35
SAY
₹56.35
D-02/SOURCEPRINTED PAGE 1124
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1124

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1124. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSDISMANTLING AND DEMOLISHING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.