Dismantling precast concrete or stone slabs in walls, partition walls etc. including stacking within 50 metres lead
- Item number
- 15.40.2
- Analysis basis
- 10 sqm
- Priced inputs
- 4
- Derived rate
- ₹433.55/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.40.2 (Dismantling precast concrete or stone slabs in walls, partition walls etc. including stacking within 50 metres lead : Thickness above 40 mm up to 75 mm) is derived from 4 priced inputs for 10 sqm and works out to ₹433.55 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0124 | LAB | Mason 2nd classMason 2nd class | day | 0.3 | 816.00 | 244.80 |
| 0114 | LAB | Beldar | day | 3 | 736.00 | 2,208.00 |
| 0115 | LAB | Coolie | day | 0.75 | 736.00 | 552.00 |
| 9999 | MAT | Sundries | L.S. | 18.85 | 2.27 | 42.79 |
- TOTAL
- 3,047.59
- Add 1 % Water charges on “W”
- +30.48
- TOTAL
- 3,078.07
- Add GST on “X” (multiplying factor 0.2127)
- +654.71
- TOTAL
- 3,732.78
- Add 15% CPOH on “Y”
- +559.92
- TOTAL
- 4,292.70
- Add Cess @ 1% on “Z”
- +42.93
- Cost of 10.00 sqm
- 4,335.63
- Cost of 1.00 sqm
- 433.56
- SAY
- ₹433.55
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1124
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1124. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.