CPWD Analysis of Rates · Dismantling and Demolishing
Dismantling and stacking within 50 metres lead, fencing posts or struts including all earth work and dismantling of concrete etc. in base of
T’ or ‘L’ iron or pipe
- Item number
- 15.34.1
- Analysis basis
- Detail of cost for each
- Priced inputs
- 5
- Derived rate
- ₹230.90
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.34.1 — Dismantling and stacking within 50 metres lead, fencing posts or struts including all earth work and dismantling of concrete etc. in base of: T’ or ‘L’ iron or pipe — is derived from 5 priced inputs and works out to ₹230.90 after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0114 | BeldarLabour | day | 0.107 | 736.00 | 78.75 |
| 0115 | CoolieLabour | day | 0.067 | 736.00 | 49.31 |
| 9999 | Excavation, transporting and stacking the posts to the required place within 50 metres lead, refilling the pit and dressing the sameMaterial | L.S. | 0.26 | 2.27 | 0.59 |
| 9999 | Extra for lifting of R.C.C. posts being heavier than L iron and cleaning the posts of stacking concreteMaterial | L.S. | 13.39 | 2.27 | 30.40 |
| 9999 | SundriesMaterial | L.S. | 1.43 | 2.27 | 3.25 |
- TOTAL
- 162.30
- Add 1 % Water charges on “W”
- 1.62
- TOTAL
- 163.92
- Add GST on “X” (multiplying factor 0.2127)
- 34.87
- TOTAL
- 198.79
- Add 15% CPOH on “Y”
- 29.82
- TOTAL
- 228.61
- Add Cess @ 1% on “Z”
- 2.29
- Cost of each
- 230.90
- Say
- 230.90
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1120. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works