CPWD Analysis of Rates · Dismantling and Demolishing

Dismantling wooden ballies in posts and struts including stacking within 50metres lead

Item number
15.33
Analysis basis
Detail of cost for 50 metre
Priced inputs
3
Derived rate
20.95 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.33 Dismantling wooden ballies in posts and struts including stacking within 50metres lead — is derived from 3 priced inputs for 50 metre and works out to ₹20.95 per metre after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
0114BeldarLabourday0.5736.00368.00
0115CoolieLabourday0.5736.00368.00
9999SundriesMaterialL.S.0.522.271.18
TOTAL
737.18
Add 1 % Water charges on “W”
7.37
TOTAL
744.55
Add GST on “X” (multiplying factor 0.2127)
158.37
TOTAL
902.92
Add 15% CPOH on “Y”
135.44
TOTAL
1,038.36
Add Cess @ 1% on “Z”
10.38
Cost of 50.00 metre
1,048.74
Cost of 1.00 metre
20.97
Say
20.95

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1119. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.