CPWD Analysis of Rates · Dismantling and Demolishing

Demolishing thatch roofing including mats, bamboo, jaffari etc. complete including stacking of serviceable material and disposal of unserviceable material within 50 metres lead

Item number
15.32
Analysis basis
Detail of cost for 10 sqm
Priced inputs
2
Derived rate
57.70 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.32 Demolishing thatch roofing including mats, bamboo, jaffari etc. complete including stacking of serviceable material and disposal of unserviceable material within 50 metres lead — is derived from 2 priced inputs for 10 sqm and works out to ₹57.70 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
0114BeldarLabourday0.54736.00397.44
9999SundriesMaterialL.S.3.642.278.26
TOTAL
405.70
Add 1 % Water charges on “W”
4.06
TOTAL
409.76
Add GST on “X” (multiplying factor 0.2127)
87.16
TOTAL
496.92
Add 15% CPOH on “Y”
74.54
TOTAL
571.46
Add Cess @ 1% on “Z”
5.71
Cost of 10.00 sqm
577.17
Cost of 1.00 sqm
57.72
Say
57.70

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1119. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works