Demolishing thatch roofing including mats, bamboo, jaffari etc. complete including stacking of serviceable material and disposal of unserviceable material within 50 metres lead

Item number
15.32
Analysis basis
10 sqm
Priced inputs
2
Derived rate
₹57.70/ SQM
D-01/RATE ANALYSISITEM 15.32

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.32 (Demolishing thatch roofing including mats, bamboo, jaffari etc. complete including stacking of serviceable material and disposal of unserviceable material within 50 metres lead) is derived from 2 priced inputs for 10 sqm and works out to ₹57.70 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 15.32DETAIL OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0114LABBeldarday0.54736.00397.44
9999MATSundriesL.S.3.642.278.26
BUILD-UP TO RATE
TOTAL
405.70
Add 1 % Water charges on “W”
+4.06
TOTAL
409.76
Add GST on “X” (multiplying factor 0.2127)
+87.16
TOTAL
496.92
Add 15% CPOH on “Y”
+74.54
TOTAL
571.46
Add Cess @ 1% on “Z”
+5.71
Cost of 10.00 sqm
577.17
Cost of 1.00 sqm
57.72
SAY
₹57.70
D-02/SOURCEPRINTED PAGE 1119
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1119

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1119. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.