Skip to main content

CPWD Analysis of Rates · Dismantling and Demolishing

Dismantling tiled roofing with battens, boarding etc. complete including stacking of serviceable material and disposal of unserviceable material within 50 metres lead

Item number
15.31
Analysis basis
Detail of cost for 10 sqm
Priced inputs
3
Derived rate
209.90 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.31 Dismantling tiled roofing with battens, boarding etc. complete including stacking of serviceable material and disposal of unserviceable material within 50 metres lead — is derived from 3 priced inputs for 10 sqm and works out to ₹209.90 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
0114BeldarLabourday1.73736.001,273.28
0115CoolieLabourday0.25736.00184.00
9999SundriesMaterialL.S.8.062.2718.30
TOTAL
1,475.58
Add 1 % Water charges on “W”
14.76
TOTAL
1,490.34
Add GST on “X” (multiplying factor 0.2127)
317.00
TOTAL
1,807.34
Add 15% CPOH on “Y”
271.10
TOTAL
2,078.44
Add Cess @ 1% on “Z”
20.78
Cost of 10.00 sqm
2,099.22
Cost of 1.00 sqm
209.92
Say
209.90

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1118. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works