CPWD Analysis of Rates · Dismantling and Demolishing

Taking out doors, windows and clerestory window shutters (steel or wood) including stacking within 50 metres lead

Of area beyond 3 sq. metres

Item number
15.13.2
Analysis basis
Detail of cost for each
Priced inputs
3
Derived rate
188.90

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.13.2 Taking out doors, windows and clerestory window shutters (steel or wood) including stacking within 50 metres lead : Of area beyond 3 sq. metres — is derived from 3 priced inputs and works out to ₹188.90 after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
0112Carpenter 2nd classLabourday0.07816.0057.12
0114BeldarLabourday0.1736.0073.60
9999SundriesMaterialL.S.0.912.272.07
TOTAL
132.79
Add 1 % Water charges on “W”
1.33
TOTAL
134.12
Add GST on “X” (multiplying factor 0.2127)
28.53
TOTAL
162.65
Add 15% CPOH on “Y”
24.40
TOTAL
187.05
Add Cess @ 1% on “Z”
1.87
Cost of each
188.92
Say
188.90

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1108. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.