Dismantling dressed stone work ashlar face stone work, marble work or precast concrete work manually/ by mechanical means including stacking of serviceable and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge

In cement mortar
Item number
15.10.2
Analysis basis
1 cum
Priced inputs
3
Derived rate
₹2,877.75/ CUM
D-01/RATE ANALYSISITEM 15.10.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.10.2 (Dismantling dressed stone work ashlar face stone work, marble work or precast concrete work manually/ by mechanical means including stacking of serviceable and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge : In cement mortar) is derived from 3 priced inputs for 1 cum and works out to ₹2,877.75 per cum after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 15.10.2DETAIL OF COST FOR 1 CUM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0114LABBeldarday1.55736.001,140.80
0115LABCoolieday1.19736.00875.84
9999MATSundriesL.S.2.732.276.20
BUILD-UP TO RATE
TOTAL
2,022.84
Add 1 % Water charges on “W”
+20.23
TOTAL
2,043.07
Add GST on “X” (multiplying factor 0.2127)
+434.56
TOTAL
2,477.63
Add 15% CPOH on “Y”
+371.64
TOTAL
2,849.27
Add Cess @ 1% on “Z”
+28.49
Cost of 1.00 cum
2,877.76
SAY
₹2,877.75
D-02/SOURCEPRINTED PAGE 1106
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1106

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1106. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSDISMANTLING AND DEMOLISHING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.