CPWD Analysis of Rates · Dismantling and Demolishing

Removing mortar from and cleaning stones and concrete articles (net quantity of stacks of cleaned materials will be measured)

In lime mortar

Item number
15.11.1
Analysis basis
Detail of cost for 1 cum
Priced inputs
4
Derived rate
478.55 / cum

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.11.1 Removing mortar from and cleaning stones and concrete articles (net quantity of stacks of cleaned materials will be measured): In lime mortar — is derived from 4 priced inputs for 1 cum and works out to ₹478.55 per cum after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
0124Mason 2nd classMason 2nd classLabourday0.05816.0040.80
0114BeldarLabourday0.2736.00147.20
0115CoolieLabourday0.2736.00147.20
9999SundriesMaterialL.S.0.522.271.18
TOTAL
336.38
Add 1 % Water charges on “W”
3.36
TOTAL
339.74
Add GST on “X” (multiplying factor 0.2127)
72.26
TOTAL
412.00
Add 15% CPOH on “Y”
61.80
TOTAL
473.80
Add Cess @ 1% on “Z”
4.74
Cost of 1.00 cum
478.54
Say
478.55

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1106. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.