CPWD Analysis of Rates · Dismantling and Demolishing
Cutting ballies or wooden posts of fencing at the point of projection above the concrete or ground and stacking the same within 50 metres lead
- Item number
- 15.35
- Analysis basis
- Detail of cost for 1 ballie (post)
- Priced inputs
- 2
- Derived rate
- ₹13.45 / ballie
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.35 — Cutting ballies or wooden posts of fencing at the point of projection above the concrete or ground and stacking the same within 50 metres lead — is derived from 2 priced inputs for 1 ballie and works out to ₹13.45 per ballie after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 9999 | CuttingMaterial | L.S. | 2.73 | 2.27 | 6.20 |
| 9999 | Transporting and stackingMaterial | L.S. | 1.43 | 2.27 | 3.25 |
- TOTAL
- 9.45
- Add 1 % Water charges on “W”
- 0.09
- TOTAL
- 9.54
- Add GST on “X” (multiplying factor 0.2127)
- 2.03
- TOTAL
- 11.57
- Add 15% CPOH on “Y”
- 1.74
- TOTAL
- 13.31
- Add Cess @ 1% on “Z”
- 0.13
- Cost of each
- 13.44
- Say
- 13.45
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1121. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.