Cutting ballies or wooden posts of fencing at the point of projection above the concrete or ground and stacking the same within 50 metres lead

Item number
15.35
Analysis basis
1 ballie
Priced inputs
2
Derived rate
₹13.45/ BALLIE
D-01/RATE ANALYSISITEM 15.35

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.35 (Cutting ballies or wooden posts of fencing at the point of projection above the concrete or ground and stacking the same within 50 metres lead) is derived from 2 priced inputs for 1 ballie and works out to ₹13.45 per ballie after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 15.35DETAIL OF COST FOR 1 BALLIE (POST)
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
9999MATCuttingL.S.2.732.276.20
9999MATTransporting and stackingL.S.1.432.273.25
BUILD-UP TO RATE
TOTAL
9.45
Add 1 % Water charges on “W”
+0.09
TOTAL
9.54
Add GST on “X” (multiplying factor 0.2127)
+2.03
TOTAL
11.57
Add 15% CPOH on “Y”
+1.74
TOTAL
13.31
Add Cess @ 1% on “Z”
+0.13
Cost of each
13.44
SAY
₹13.45
D-02/SOURCEPRINTED PAGE 1121
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1121

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1121. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSDISMANTLING AND DEMOLISHING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.