Cutting ballies or wooden posts of fencing at the point of projection above the concrete or ground and stacking the same within 50 metres lead

Item number
15.35
Analysis basis
Detail of cost for 1 ballie (post)
Priced inputs
2
Derived rate
13.45 / ballie

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.35 Cutting ballies or wooden posts of fencing at the point of projection above the concrete or ground and stacking the same within 50 metres lead — is derived from 2 priced inputs for 1 ballie and works out to ₹13.45 per ballie after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
9999CuttingMaterialL.S.2.732.276.20
9999Transporting and stackingMaterialL.S.1.432.273.25
TOTAL
9.45
Add 1 % Water charges on “W”
0.09
TOTAL
9.54
Add GST on “X” (multiplying factor 0.2127)
2.03
TOTAL
11.57
Add 15% CPOH on “Y”
1.74
TOTAL
13.31
Add Cess @ 1% on “Z”
0.13
Cost of each
13.44
Say
13.45

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1121. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.