Cutting ballies or wooden posts of fencing at the point of projection above the concrete or ground and stacking the same within 50 metres lead
- Item number
- 15.35
- Analysis basis
- 1 ballie
- Priced inputs
- 2
- Derived rate
- ₹13.45/ BALLIE
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.35 (Cutting ballies or wooden posts of fencing at the point of projection above the concrete or ground and stacking the same within 50 metres lead) is derived from 2 priced inputs for 1 ballie and works out to ₹13.45 per ballie after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 9999 | MAT | Cutting | L.S. | 2.73 | 2.27 | 6.20 |
| 9999 | MAT | Transporting and stacking | L.S. | 1.43 | 2.27 | 3.25 |
- TOTAL
- 9.45
- Add 1 % Water charges on “W”
- +0.09
- TOTAL
- 9.54
- Add GST on “X” (multiplying factor 0.2127)
- +2.03
- TOTAL
- 11.57
- Add 15% CPOH on “Y”
- +1.74
- TOTAL
- 13.31
- Add Cess @ 1% on “Z”
- +0.13
- Cost of each
- 13.44
- SAY
- ₹13.45
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1121
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1121. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.