Dismantling barbed wire or flexible wire rope in fencing including making rolls and stacking within 50 metres lead

Item number
15.36
Analysis basis
1 quintal
Priced inputs
2
Derived rate
₹36.80/ QUINTAL
D-01/RATE ANALYSISITEM 15.36

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.36 (Dismantling barbed wire or flexible wire rope in fencing including making rolls and stacking within 50 metres lead) is derived from 2 priced inputs for 1 quintal and works out to ₹36.80 per quintal after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 15.36DETAIL OF COST FOR 1 QUINTAL
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0114LABBeldarday3.5736.002,576.00
9999MATSundriesL.S.5.332.2712.10
BUILD-UP TO RATE
TOTAL
2,588.10
Add 1 % Water charges on “W”
+25.88
TOTAL
2,613.98
Add GST on “X” (multiplying factor 0.2127)
+555.99
TOTAL
3,169.97
Add 15% CPOH on “Y”
+475.50
TOTAL
3,645.47
Add Cess @ 1% on “Z”
+36.45
Cost of 1.00 quintal
3,681.92
Cost of 1.00 kg
36.82
SAY
₹36.80
D-02/SOURCEPRINTED PAGE 1121
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1121

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1121. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.