Dismantling barbed wire or flexible wire rope in fencing including making rolls and stacking within 50 metres lead

Item number
15.36
Analysis basis
Detail of cost for 1 quintal
Priced inputs
2
Derived rate
36.80 / quintal

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.36 Dismantling barbed wire or flexible wire rope in fencing including making rolls and stacking within 50 metres lead — is derived from 2 priced inputs for 1 quintal and works out to ₹36.80 per quintal after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
0114BeldarLabourday3.5736.002,576.00
9999SundriesMaterialL.S.5.332.2712.10
TOTAL
2,588.10
Add 1 % Water charges on “W”
25.88
TOTAL
2,613.98
Add GST on “X” (multiplying factor 0.2127)
555.99
TOTAL
3,169.97
Add 15% CPOH on “Y”
475.50
TOTAL
3,645.47
Add Cess @ 1% on “Z”
36.45
Cost of 1.00 quintal
3,681.92
Cost of 1.00 kg
36.82
Say
36.80

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1121. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.