CPWD Analysis of Rates · Dismantling and Demolishing

Demolishing brick work manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge

In mud mortar

Item number
15.7.1
Analysis basis
Detail of cost for 1 cum
Priced inputs
3
Derived rate
704.90 / cum

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.7.1 Demolishing brick work manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge In mud mortar — is derived from 3 priced inputs for 1 cum and works out to ₹704.90 per cum after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
0114BeldarLabourday0.3736.00220.80
0115CoolieLabourday0.37736.00272.32
9999SundriesMaterialL.S.1.042.272.36
TOTAL
495.48
Add 1 % Water charges on “W”
4.95
TOTAL
500.43
Add GST on “X” (multiplying factor 0.2127)
106.44
TOTAL
606.87
Add 15% CPOH on “Y”
91.03
TOTAL
697.90
Add Cess @ 1% on “Z”
6.98
Cost of 1.00 cum
704.88
Say
704.90

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1102. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.