Extra for scrapping, cleaning and straightening reinforcement from R.C.C. or R.B. work

Item number
15.6
Analysis basis
10 Nos
Priced inputs
3
Derived rate
₹9.05/ KG
D-01/RATE ANALYSISITEM 15.6

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.6 (Extra for scrapping, cleaning and straightening reinforcement from R.C.C. or R.B. work) is derived from 3 priced inputs for 10 Nos and works out to ₹9.05 per kg after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 6 metres long 16 mm dia bars @ 1.58 kg/metre
  • Total weight = 94.80 kg = 0.948 quintal
ANALYSIS OF RATES · ITEM 15.6DETAIL OF COST FOR 10 NOS
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0103LABBlacksmith 2nd classday0.25816.00204.00
0114LABBeldarday0.5736.00368.00
9999MATSundriesL.S.13.392.2730.40
BUILD-UP TO RATE
TOTAL
602.40
Add 1 % Water charges on “W”
+6.02
TOTAL
608.42
Add GST on “X” (multiplying factor 0.2127)
+129.41
TOTAL
737.83
Add 15% CPOH on “Y”
+110.67
TOTAL
848.50
Add Cess @ 1% on “Z”
+8.49
Cost of 94.80 kg
856.99
Cost of 1.00 kg
9.04
SAY
₹9.05
D-02/SOURCEPRINTED PAGE 1101
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1101

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1101. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.