Extra for scrapping, cleaning and straightening reinforcement from R.C.C. or R.B. work
- Item number
- 15.6
- Analysis basis
- 10 Nos
- Priced inputs
- 3
- Derived rate
- ₹9.05/ KG
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.6 (Extra for scrapping, cleaning and straightening reinforcement from R.C.C. or R.B. work) is derived from 3 priced inputs for 10 Nos and works out to ₹9.05 per kg after water charges, GST, CPOH and cess. The full build-up is below.
- 6 metres long 16 mm dia bars @ 1.58 kg/metre
- Total weight = 94.80 kg = 0.948 quintal
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0103 | LAB | Blacksmith 2nd class | day | 0.25 | 816.00 | 204.00 |
| 0114 | LAB | Beldar | day | 0.5 | 736.00 | 368.00 |
| 9999 | MAT | Sundries | L.S. | 13.39 | 2.27 | 30.40 |
- TOTAL
- 602.40
- Add 1 % Water charges on “W”
- +6.02
- TOTAL
- 608.42
- Add GST on “X” (multiplying factor 0.2127)
- +129.41
- TOTAL
- 737.83
- Add 15% CPOH on “Y”
- +110.67
- TOTAL
- 848.50
- Add Cess @ 1% on “Z”
- +8.49
- Cost of 94.80 kg
- 856.99
- Cost of 1.00 kg
- 9.04
- SAY
- ₹9.05
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1101
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1101. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.