CPWD Analysis of Rates · Dismantling and Demolishing
Extra for scrapping, cleaning and straightening reinforcement from R.C.C. or R.B. work
- Item number
- 15.6
- Analysis basis
- Detail of cost for 10 Nos
- Priced inputs
- 3
- Derived rate
- ₹9.05 / kg
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.6 — Extra for scrapping, cleaning and straightening reinforcement from R.C.C. or R.B. work — is derived from 3 priced inputs for 10 Nos and works out to ₹9.05 per kg after water charges, GST, CPOH and cess. The full build-up is below.
- 6 metres long 16 mm dia bars @ 1.58 kg/metre
- Total weight = 94.80 kg = 0.948 quintal
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0103 | Blacksmith 2nd classLabour | day | 0.25 | 816.00 | 204.00 |
| 0114 | BeldarLabour | day | 0.5 | 736.00 | 368.00 |
| 9999 | SundriesMaterial | L.S. | 13.39 | 2.27 | 30.40 |
- TOTAL
- 602.40
- Add 1 % Water charges on “W”
- 6.02
- TOTAL
- 608.42
- Add GST on “X” (multiplying factor 0.2127)
- 129.41
- TOTAL
- 737.83
- Add 15% CPOH on “Y”
- 110.67
- TOTAL
- 848.50
- Add Cess @ 1% on “Z”
- 8.49
- Cost of 94.80 kg
- 856.99
- Cost of 1.00 kg
- 9.04
- Say
- 9.05
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1101. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.